All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install and commission electrical measuring instruments and control devices |
SAQA US ID | UNIT STANDARD TITLE | |||
10260 | Install and commission electrical measuring instruments and control devices | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 5 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2007-04-03 | 2009-02-18 | SAQA 0160/05 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2010-02-18 | 2013-02-18 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard is replaced by: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
259078 | Install and commission electrical metering units, measuring instruments and control devices | Level 2 | NQF Level 02 | 8 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering; Generation; Distribution; Transmission, Construction and Renewable Energy Sector
A person credited with this unit standard will be able to: Install, connect and commission electrical metering units or measuring instruments and their control devices to monitor electrical values This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical engineering and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills, attitude and / or equivalent:
|
UNIT STANDARD RANGE |
a. OHS Act b. SABS 0142 c. Local Authority requirements a. Safety procedures as given in Safety manuals b. Policy procedures as given in Policy manuals c. Installing procedures as given in Manufacturers` and Company maintenance manuals d. Maintaining procedure given in Manufacturers` and Company maintenance manuals a. Dimensions of components, b. Weight of components, c. Type of material from which components were manufactured as given in: 1. Manufacturers` maintenance manuals 2. Manufacturer catalogues 3. Company maintenance manuals The work done will be according to the appropriate of the following specifications, standards and/or procedures: |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Explain the requirements pertaining to install electrical metering units. |
OUTCOME NOTES |
Explain the requirements pertaining to install electrical metering units or measuring instruments and control devices. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. The sequence of events is explained. |
ASSESSMENT CRITERION 2 |
2. The reason for matching ratios is given. |
ASSESSMENT CRITERION 3 |
3. The purpose of the control device is explained. |
ASSESSMENT CRITERION 4 |
4. Selection of equipment is explained. |
SPECIFIC OUTCOME 2 |
Plan to install and connect electrical measuring instruments with their relative control devices. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Appropriate documentation is acquired. |
ASSESSMENT CRITERION 2 |
2. Job instructions are communicated with team leader. |
ASSESSMENT CRITERION 3 |
3. Circuit, -wiring- and mounting diagrams are drawn. |
ASSESSMENT CRITERION 4 |
4. Appropriate meter units or instruments and control devices are identify and selected. |
SPECIFIC OUTCOME 3 |
Prepare, install and connect electrical metering units or measuring instruments and control devices. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1.Holes for instruments are marked out and cut. |
ASSESSMENT CRITERION 2 |
2.Measuring instruments and control devices are mounted / installed. |
ASSESSMENT CRITERION 3 |
3.Measuring instruments and control devices are connected. |
ASSESSMENT CRITERION 4 |
4.Safety, good housekeeping and correct environmental practices are followed before, during and after performance. |
ASSESSMENT CRITERION 5 |
4. Safety, good housekeeping and correct environmental practices are followed before, during and after performance. |
ASSESSMENT CRITERION 6 |
1. Holes for meter units or instruments are marked out and cut. |
ASSESSMENT CRITERION 7 |
2. Metering units or measuring instruments and control devices are mounted / installed. |
ASSESSMENT CRITERION 8 |
3. Metering units or measuring instruments and control devices are connected. |
SPECIFIC OUTCOME 4 |
Commission electrical metering units or measuring instruments. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Compare wiring with drawing. |
ASSESSMENT CRITERION 2 |
2. Continuity, earth continuity, insulation resistance, etc. tests are done. |
ASSESSMENT CRITERION 3 |
3. Visual faults accurately identified and repaired. |
ASSESSMENT CRITERION 4 |
4. Actual and expected readings are compared. |
ASSESSMENT CRITERION 5 |
5. Metering units or measuring instruments are sealed according to applicable standards. |
SPECIFIC OUTCOME 5 |
Complete work activity. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Work area is cleaned in accordance with house keeping standards. |
ASSESSMENT CRITERION 2 |
2. Tools and equipment are stored in their correct place in accordance with work place practices and manufacturer`s specifications. |
ASSESSMENT CRITERION 3 |
3. Waste materials are disposed of according to work site procedures and statutory requirements and environmental standards. |
ASSESSMENT CRITERION 4 |
4. Documentation is completed in detail and submitted to meet work site standards and procedures. |
ASSESSMENT CRITERION RANGE |
Written data, records, electronic data, test or inspection reports. |
ASSESSMENT CRITERION 5 |
5. Completion of job is reported to relevant parties. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
1. Anyone assessing a learner against this unit standard must be registered as an assessor with the relevant ETQA.
2. Any institution offering learning that will enable achievement of this unit standard must be accredited as a provider through the relevant ETQA by SAQA. 3. Moderation of assessment will be overseen by the relevant ETQA according to the moderation guidelines in the relevant qualification and the agreed ETQA prodedures. |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO WORKING |
Tasks performed by using responsible thinking and decision making in relation to the use of tools and equipment; choice and use of relevant personal protecting equipment and safety equipment. |
UNIT STANDARD CCFO ORGANISING |
Organise oneself and one`s activities responsibly and effectively in the ability to follow instructions when working by ones self or in a work team, ensure safe execution of work activities. |
UNIT STANDARD CCFO COLLECTING |
Collect, evaluate, organise and critically evaluate information related to install and commission electrical metering units or measuring instruments and control devices. |
UNIT STANDARD CCFO COMMUNICATING |
Effective use of communication methods when communicating with supervisor. |
UNIT STANDARD CCFO SCIENCE |
Use science and technology effectively and critically, showing responsibility towards the environmental and the health of others in install and commission electrical metering units or measuring instruments and control devices in such a way by ensuring that all safety and environmental conditions are considered. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
UNIT STANDARD NOTES |
This unit standard has been replaced by unit standard 259078, which is "Install and commission electrical metering units, measuring instruments and control devices", Level 2, 8 credits.
This Unit Standard was originally registered on 12 June 2002 under SAQA decision number 0742/02. It has been re-registered on 11 February 2004 under SAQA 2552/04. Credits Total hours required by the learner to achieve the required outcomes: Activity Hours Classroom learning 15 On-the-job learning 25 Self directed learning 5 Coaching required 5 Other Total 50 Credits achieved 5 |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 48475 | National Certificate: Electrical Engineering | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2009-02-18 | Was EWSETA until Last Date for Achievement |
Core | 20419 | National Certificate: Electrical Engineering | Level 3 | NQF Level 03 | Passed the End Date - Status was "Registered" |
2004-02-10 | Was EWSETA until Last Date for Achievement |
Elective | 58288 | National Certificate: Electro-Mechanics | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |