All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Carry out a detailed inspection on an overhead trolley line |
SAQA US ID | UNIT STANDARD TITLE | |||
110387 | Carry out a detailed inspection on an overhead trolley line | |||
ORIGINATOR | ||||
SGB Mining and Minerals | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 06 - Manufacturing, Engineering and Technology | Fabrication and Extraction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 4 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
This unit standard will be useful to people who are required to inspect an overhead trolley line.
People credited with this unit standard are able to |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The credit calculation is based on the assumption that learners are already competent in terms of the following outcomes or areas of learning when starting to learn towards this unit standard:
The ability to: Knowledge of: |
UNIT STANDARD RANGE |
The following scope and context applies to the whole unit standard:
A detailed inspection must include: Specific range statements are provided in the body of the unit standard where they apply to particular specific outcomes or assessment criteria. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Explain the requirements for an inspection on an overhead trolley line. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. The purpose of inspecting an overhead trolley line is explained in accordance with specified requirements. |
ASSESSMENT CRITERION 2 |
2. The selection criteria of overhead conductors and feeder cables are explained, with reference to size, voltage rating and characteristics of material. |
ASSESSMENT CRITERION 3 |
3. The application of the different types of cleaning material, equipment and solvents are explained with reference to health, safety and impact on the environment. |
ASSESSMENT CRITERION 4 |
4. The various cleaning methods are explained in accordance with specified requirements. |
SPECIFIC OUTCOME 2 |
Prepare to inspect the overhead trolley line. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Personal protective equipment is examined and used in a manner that protects the individual in accordance with specified requirements. |
ASSESSMENT CRITERION 2 |
2. Tools, material and equipment are selected, examined and transported in accordance with specified requirements. |
ASSESSMENT CRITERION 3 |
3. Permission to enter the workplace where applicable is obtained in accordance with specified requirements. |
ASSESSMENT CRITERION 4 |
4. Affected parties are notified of scheduled planned inspection in accordance with specified requirements. |
ASSESSMENT CRITERION 5 |
5. The workplace is examined for hazardous and substandard conditions, which are addressed in accordance with specified requirements. |
ASSESSMENT CRITERION 6 |
6. The consequences of not preparing to inspect the overhead trolley line, in line with specific requirements are explained with reference to personal and team safety, impact on the environment, production costs and lost time. |
SPECIFIC OUTCOME 3 |
Inspect the overhead trolley line. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Personal protective equipment is used in a manner that protects the individual in accordance with specified requirements. |
ASSESSMENT CRITERION 2 |
2. Tools, material and equipment are used in accordance with specified requirements. |
ASSESSMENT CRITERION 3 |
3. The power is switched off and lockout procedures are adhered to in accordance with specified requirements. |
ASSESSMENT CRITERION 4 |
4. The overhead trolley line is inspected and defects addressed in accordance with specified requirements. |
ASSESSMENT CRITERION 5 |
5. Hazards and risks directly related to the inspection of the overhead trolley line are identified and addressed in accordance with specified requirements. |
ASSESSMENT CRITERION 6 |
6. Interpersonal interaction is positive, consistent with specified requirements, promotes effective teamwork and avoids dysfunctional conflict. |
ASSESSMENT CRITERION 7 |
7. The consequences of not inspecting the overhead trolley line in accordance with specified requirements are explained with reference to personal and team safety, impact on the environment, production costs and lost time. |
SPECIFIC OUTCOME 4 |
Test and prepare the trolley line for operation. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. The integrity of the overhead trolley line is tested in accordance with specified requirements. |
ASSESSMENT CRITERION 2 |
2. The power is switched on and operational tests are conducted in accordance with specified requirements. |
ASSESSMENT CRITERION 3 |
3. The integrity of the earth system and the operation of the earth leakage are tested in accordance with specified requirements. |
ASSESSMENT CRITERION 4 |
4. The operation of the system is tested in accordance with specified requirements. |
ASSESSMENT CRITERION 5 |
5. The workplace is cleaned to comply with specified housekeeping practices. |
ASSESSMENT CRITERION 6 |
6. Tools, material and equipment are cleaned, inspected and stored in accordance with specified requirements. |
ASSESSMENT CRITERION 7 |
7. The feedback report complies with specified requirements. |
ASSESSMENT CRITERION 8 |
8. The consequences of not testing and not preparing the overhead trolley line for operation is explained with reference to personal and team safety, impact on the environment, production costs and lost time. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
1. Anyone assessing a learner against this unit standard must be registered as an assessor with the relevant ETQA.
2. Any institution offering learning that will enable achievement of this unit standard must be accredited as a provider with the relevant ETQA and SAQA. 3. Moderation of assessment will be overseen by the relevant ETQA according to the moderation guidelines in the relevant qualification and the agreed ETQA procedures. |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Essential embedded knowledge will be assessed through assessment of the specific outcomes in terms of the stipulated assessment criteria. Candidates are unlikely to achieve all the specific outcomes, to the standards described in the assessment criteria, without knowledge of the listed embedded knowledge. This means that for the most part, the possession or lack of the knowledge can be directly inferred from the quality of the candidate`s performance. Where direct assessment of knowledge is required, assessment criteria have been included in the body of the unit standard.
The following embedded knowledge is addressed in an integrated way in the unit standard: |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems and make decisions using critical and creative thinking.
|
UNIT STANDARD CCFO WORKING |
Work effectively with others as members of a team, group, organisation or community.
|
UNIT STANDARD CCFO ORGANISING |
Organise and manage themselves and their activities responsibly and effectively.
|
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information.
|
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively, using visual, mathematical and / or language skills in the modes of oral and / or written presentations.
|
UNIT STANDARD CCFO SCIENCE |
Use science and technology effectively and critically showing responsibility towards the environment and health of others.
Note: The use of science and technology is not relevant for this unit standard. |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate an understanding of the world as a set of related systems by recognising that problem-solving contexts do not exist in isolation.
|
UNIT STANDARD ASSESSOR CRITERIA |
Assessors should keep the following principles in mind when designing and conducting assessments against this unit standard:
|
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Terminology
Specified requirments Specified requirements include legal and site-specific requirements and are contained in one or more of the following documents: Legal Site specific |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 73313 | National Certificate: Electrical Engineering | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | 4 TOPS ACADEMY |
2. | Better Best Agri Development |
3. | Double ST Training and Skills Development |
4. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
5. | Goitsebasadi Construction Project |
6. | KP ACADEMY (PTY) LTD |
7. | Motheo TVET College |
8. | MSC ARTISAN ACADEMY |
9. | PCD College cc |
10. | POWER SYSTEMS TRAINING, CAPE TOWN |
11. | Protech Training (Pty) Ltd |
12. | Umfolozi FET College |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |