All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Finish off and hand over structural works |
SAQA US ID | UNIT STANDARD TITLE | |||
116577 | Finish off and hand over structural works | |||
ORIGINATOR | ||||
SGB Civil Engineering Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Civil Engineering Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 12 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2007-05-15 | 2009-05-13 | SAQA 0160/05 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2010-05-13 | 2013-05-13 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard is replaced by: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
262591 | Finish off steel structure and explain hand over procedures | Level 3 | NQF Level 03 | 6 |
PURPOSE OF THE UNIT STANDARD |
The qualifying learner is capable of:
Finishing off structural work, dismantling structures and handing over completed structures in accordance with safety legislation and industry procedures. Demonstrate knowledge of Technical information for the securing of fastenings or specialised attachments. Types and use of measuring equipment. Occupational Health and Safety Act in relation to walkways, access, dismantling and storing of lifting equipment and accessories, storage of consumables used to operate lifting equipment. The contribution to The National Skills Development Strategy is the key developmental interface between learners and new competencies to be achieved. Learners who master the applied competence described in this unit standard will contribute to the development of a professional community of Structural Steel Erectors who are able to competently use science and technology when finishing off structural work, dismantling structures and handing over structures. In addition, the learner's ability to interpret and carry out instructions in a competent manner will lead to enhanced quality of workmanship and reduce the costs associated with work having to be redone and the resultant over-run on deadlines. An enhanced understanding of safety legislation and safety common sense will lead to a notable reduction in the high and often fatal risks associated with work conducted at heights well above ground level. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and / or equivalent:
Language and Communication in an official language at NQF Level 3 Language and Communication in a second official language at NQF Level 2 Mathematics at NQF Level 3 Read and interpret drawings and specifications at NQF Level 3 |
UNIT STANDARD RANGE |
The typical scope of this unit standard:
All tasks and activities associated with the finishing off and handing over of structural steelwork are carried out in accordance with: |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Finish off structural work. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Fastening of structures is completed in accordance with design engineer's specifications, safety legislation requirements and standard industry procedures |
ASSESSMENT CRITERION 2 |
Structures are aligned and levelled in accordance with design engineer's specifications |
ASSESSMENT CRITERION 3 |
Structures are protected against corrosion in accordance with contract specifications |
ASSESSMENT CRITERION 4 |
Structures are fire-proofed where applicable in accordance with contract specifications |
ASSESSMENT CRITERION 5 |
Intermittent quality checks are conducted, recorded, signed and certified in accordance with safety legislation and quality control system requirements |
ASSESSMENT CRITERION 6 |
Structures are finished off and completed in accordance with the Erection Method Statement and specification requirements |
ASSESSMENT CRITERION 7 |
Structures are finished off without injury to persons or damage to components and/or equipment at heights, or uncompleted structures in accordance with safety legislation and standard procedures for safe working practices |
SPECIFIC OUTCOME 2 |
Carry out amendments to structures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Structures are checked for safe access in accordance with safety legislation and contract requirements |
ASSESSMENT CRITERION 2 |
Amendments are carried out to structures in accordance with safety, client and maintenance personnel requirements |
ASSESSMENT CRITERION 3 |
Site personnel access requirements are identified, installed and commissioned in accordance with safety legislation and client requirements |
ASSESSMENT CRITERION 4 |
Access for future structural maintenance works is carried out in accordance with client requirements |
ASSESSMENT CRITERION 5 |
Structural amendments that are undertaken outside the scope of the contract are agreed and authorised in accordance with standard industry procedures |
SPECIFIC OUTCOME 3 |
Dismantle structures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Structures are dismantled without injury to persons or damage to components and/or equipment and in accordance with safety legislation requirements, manufacturer's specifications and standard industry procedures |
ASSESSMENT CRITERION 2 |
Lifting equipment and accessories are stored in accordance with safety legislation requirements, manufacturer's specifications and standard industry procedures |
ASSESSMENT CRITERION 3 |
Consumables for operating lifting equipment are stored in accordance with safety legislation and municipal by-laws and fire department requirements |
ASSESSMENT CRITERION 4 |
Local conditions which may affect continuing stability are identified and measures taken to ensure continuing stability in accordance with safety legislation requirements and standard industry procedures |
ASSESSMENT CRITERION 5 |
Load shifting equipment is dismantled without injury to persons or damage to components and/or equipment, to manufacturers' specifications and enterprise procedures |
SPECIFIC OUTCOME 4 |
Hand over structures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Final inspection is conducted by all relevant roleplayers |
ASSESSMENT CRITERION 2 |
Final inspection is recorded, signed, certified and distributed in accordance with the requirements of the quality plan |
ASSESSMENT CRITERION 3 |
All work is completed within time and cost parameters and completed structures are fit for purpose |
ASSESSMENT CRITERION 4 |
Clearance acceptance procedures are carried out in accordance with contract requirements |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems
Relates to the following specific outcomes and assessment criterias: Finish off structural work Carry out admendments to structures |
UNIT STANDARD CCFO WORKING |
Work effectively with others
Relates to the following specific outcomes and assessment criterias: Carry out admendments to structures Hand over structures |
UNIT STANDARD CCFO ORGANISING |
Employ self management
Relates to the following specific outcomes and assessment criterias: Finish off structural work Carry out admendments to structures |
UNIT STANDARD CCFO COLLECTING |
Manage information
Relates to the following specific outcomes and assessment criterias: Finish off structural work Carry out admendments to structures |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively
Relates to the following specific outcomes and assessment criterias: Finish off structural work Hand over structures |
UNIT STANDARD CCFO SCIENCE |
Demonstrate scientific and technological competence
Relates to the following specific outcomes and assessment criterias: Finish off structural work Dismantle structures |
UNIT STANDARD CCFO DEMONSTRATING |
Understand contextual world-systems
Finish off structural work Carry out admendments to structures |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
UNIT STANDARD NOTES |
This unit standard has been replaced by unit standard 262591, which is "Finish off steel structure and explain hand over procedures", Level 3, 6 credits. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 49015 | National Certificate: Construction: Structural Steel Erecting | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2009-05-13 | Was CETA until Last Date for Achievement |
Elective | 49053 | National Certificate: Supervision of Construction Processes | Level 4 | Level TBA: Pre-2009 was L4 | Passed the End Date - Status was "Reregistered" |
2018-06-30 | Was CETA until Last Date for Achievement |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | AVUXENI COMPUTER ACADEMY KZN |
2. | Eastcape Training Centre |
3. | Raubex Construction Pty (Ltd) |
4. | SEDA Construction Incubator Trust |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |