All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Perform routine operations on volume manufacturing equipment |
SAQA US ID | UNIT STANDARD TITLE | |||
12660 | Perform routine operations on volume manufacturing equipment | |||
ORIGINATOR | ||||
SGB Manufacturing and Assembly Processes | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 06 - Manufacturing, Engineering and Technology | Manufacturing and Assembly | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 10 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2004-12-02 | 2005-04-13 | SAQA 1657/04 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2006-04-13 | 2009-04-13 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard is replaced by: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
119162 | Perform routine operations on plastics manufacturing equipment | Level 3 | NQF Level 03 | 10 |
PURPOSE OF THE UNIT STANDARD |
Starting up, monitoring and shutting down the production line. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
This unit standard has been designed as part of a progression. It is one of a series of unit standards for activities below, at and above this level. The credits assigned to it are based on the assumption that I have already been assessed and have obtained credits for related activities at this level or below it.
If I have experience in these related activities but do not have such credits, I can obtain credits by being assessed through a process which recognises prior learning. If I do not have such experience, then my learning time will be increased. I can choose to be assessed and obtain credits against those other unit standards as I make progress towards the outcomes of this unit standard. |
UNIT STANDARD RANGE |
Setting parameters include:
|
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Monitor equipment and material, conduct quality checks and resolve problems. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Production outputs meet specification. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 2 |
2. Machine runs effectively - Start, stop, run. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 3 |
3. Reports and records reflect events and conditions. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 4 |
4. The person relieving me knows what the production status is. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 5 |
5. Machine started and running. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 6 |
6. Machine stopped and shut down. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
SPECIFIC OUTCOME 2 |
Start up, purge and shut down machine. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Production outputs meet specification. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 2 |
2. Machine runs effectively - Start, stop, run. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 3 |
3. Reports and records reflect events and conditions. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 4 |
4. The person relieving me knows what the production status is. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 5 |
5. Machine started and running. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 6 |
6. Machine stopped and shut down. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
SPECIFIC OUTCOME 3 |
Report and record information. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Production outputs meet specification. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 2 |
2. Machine runs effectively - Start, stop, run. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 3 |
3. Reports and records reflect events and conditions. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 4 |
4. The person relieving me knows what the production status is. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 5 |
5. Machine started and running. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
ASSESSMENT CRITERION 6 |
6. Machine stopped and shut down. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. good housekeeping 2. safe working 3. sufficient material available 4. lack of machine defects 5. Amount of rejects within limits Understanding confirmed: 1. Explain, show and discuss consequences of: |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Names & functions of:
Attributes, descriptions, characteristics & properties: Sensory cues: Purpose of: Processes, events, causes and effects, implications: Categories: Procedures and techniques Regulations, legislation, agreements, policies, standards Theory: rules, principles, laws Relationships, systems: |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems .
|
UNIT STANDARD CCFO WORKING |
Work effectively with others .
|
UNIT STANDARD CCFO ORGANISING |
Organise and manage myself and my activities.
|
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information.
|
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively.
|
UNIT STANDARD CCFO SCIENCE |
Use science and technology effectively and critically.
|
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate an understanding of the world as a set of related systems.
|
UNIT STANDARD NOTES |
This unit standard has been replaced by unit standard 119162, which is 'Perform routine operations on plastics manufacturing equipment', Level 3, 10 credits. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 20889 | National Certificate: Plastics Manufacturing | Level 3 | NQF Level 03 | Passed the End Date - Status was "Registered" |
2005-04-13 | Was MERSETA until Last Date for Achievement |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |