All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install, test and maintain an electro-pneumatic system |
SAQA US ID | UNIT STANDARD TITLE | |||
13116 | Install, test and maintain an electro-pneumatic system | |||
ORIGINATOR | ||||
SGB Manufacturing and Assembly Processes | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 06 - Manufacturing, Engineering and Technology | Manufacturing and Assembly | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 20 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
The skills, values and knowledge reflected in this unit standard are required by people in the field of mechatronics. The learning outcomes in this unit standard also contribute to the exit level outcomes required for the mechatronics NQF level 4 qualification.
Qualifying learners can interpret, install, test, programme and maintain manual and PLC based electro- pneumatic circuits. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
This unit standard has been designed to be as part of a progression. It is one of a series of unit standards for activities at and above this level. The credits assigned to it are based on the assumption that the learner is learning what is needed for this unit standard as part of his/her learning for a range of related unit standards at this level.
The credits allocated to this unit standard assume that a learner has already learned to: |
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Read and interpret electro- pneumatic circuit diagrams and related component symbols. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Electro-pneumatic circuit diagrams and related symbols read and interpreted. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 2 |
2. Manual electro-pneumatic circuits installed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 3 |
3. Lines and conductors joined and terminated. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 4 |
4. Electro-pneumatic PLC controlled circuits installed and programmed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 5 |
5. Electro-pneumatic circuits are tested and results recorded. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 6 |
6. Installations are maintained to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
SPECIFIC OUTCOME 2 |
Identify and select electro-pneumatic components. |
OUTCOME RANGE |
Electro-pneumatic components include solenoid actuated spool-type directional control valves, solenoid actuated flow control valves, one-shot valves. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Electro-pneumatic circuit diagrams and related symbols read and interpreted. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 2 |
2. Manual electro-pneumatic circuits installed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 3 |
3. Lines and conductors joined and terminated. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 4 |
4. Electro-pneumatic PLC controlled circuits installed and programmed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 5 |
5. Electro-pneumatic circuits are tested and results recorded. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 6 |
6. Installations are maintained to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
SPECIFIC OUTCOME 3 |
Install manual electro- pneumatic circuits. |
OUTCOME NOTES |
Test circuit and record results |
OUTCOME RANGE |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Electro-pneumatic circuit diagrams and related symbols read and interpreted. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 2 |
2. Manual electro-pneumatic circuits installed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 3 |
3. Lines and conductors joined and terminated. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 4 |
4. Electro-pneumatic PLC controlled circuits installed and programmed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 5 |
5. Electro-pneumatic circuits are tested and results recorded. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 6 |
6. Installations are maintained to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
SPECIFIC OUTCOME 4 |
Construct and programme an integrated PLC controlled electro-pneumatic circuit. |
OUTCOME NOTES |
Test circuit and record results |
OUTCOME RANGE |
A PLC electro-pneumatic circuit may include valve control, flow control, proportional valves, directional valves, one-shot valves |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Electro-pneumatic circuit diagrams and related symbols read and interpreted. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 2 |
2. Manual electro-pneumatic circuits installed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 3 |
3. Lines and conductors joined and terminated. |
ASSESSMENT CRITERION 4 |
4. Electro-pneumatic PLC controlled circuits installed and programmed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 5 |
5. Electro-pneumatic circuits are tested and results recorded. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 6 |
6. Installations are maintained to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
SPECIFIC OUTCOME 5 |
Maintain electro-pneumatic circuits. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Electro-pneumatic circuit diagrams and related symbols read and interpreted. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 2 |
2. Manual electro-pneumatic circuits installed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 3 |
3. Lines and conductors joined and terminated. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 4 |
4. Electro-pneumatic PLC controlled circuits installed and programmed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 5 |
5. Electro-pneumatic circuits are tested and results recorded. |
ASSESSMENT CRITERION NOTES |
Understanding confirmed:
Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 6 |
6. Installations are maintained to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
SPECIFIC OUTCOME 6 |
Work safely with care for self, fellow workers, machines, equipment, materials and the environment. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Electro-pneumatic circuit diagrams and related symbols read and interpreted. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 2 |
2. Manual electro-pneumatic circuits installed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 3 |
3. Lines and conductors joined and terminated. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 4 |
4. Electro-pneumatic PLC controlled circuits installed and programmed to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 5 |
5. Electro-pneumatic circuits are tested and results recorded. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
ASSESSMENT CRITERION 6 |
6. Installations are maintained to specifications. |
ASSESSMENT CRITERION NOTES |
Indicators:
1. Correct components are selected and used 2. Test equipment is used correctly 3. Correct tools are selected and used 4. Safe working practices are adhered to 5. Problems are reported timeously to appropriate personnel 6. A clean and tidy work environment is maintained Understanding confirmed: Respond to 'what if' and 'why' questions covering: Discuss the implications of not adhering to the sequence of activities and operations as described in the specific outcomes and making decisions inappropriate to the task. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
My assessment will be governed by the policies and guidelines of the MERSETA Education and Training Quality Assuror who has jurisdiction over this field of learning. My assessor will (at the very least) be accredited and have a technical qualification in this learning area.
I can be assessed in the language of my choice although if I have to report incidents or conditions to someone else, I will be assessed on my ability to report in the language commonly used in my working environment. I will be assessed in the workplace but I can submit documents, projects, test results and assignments that were not produced in the workplace. I can be assessed against this unit standard to obtain credits or as part of an integrated assessment for a qualification. |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Names and functions of:
Attributes, descriptions, characteristics & properties: Sensory cues: Purpose of: Processes, events, causes and effects, implications: Procedures and techniques: Regulations, legislation, agreements, policies, standards: Theory: rules, principles, laws: Relationships, systems: |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems:
|
UNIT STANDARD CCFO WORKING |
Work effectively with others:
|
UNIT STANDARD CCFO ORGANISING |
Organise and manage myself and my activities:
|
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively:
|
UNIT STANDARD CCFO SCIENCE |
Use science and technology effectively and critically:
|
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate an understanding of the world as a set of related systems:
|
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
N/A |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 48964 | Further Education and Training Certificate: Clothing, Textiles, Footwear and Leather (CTFL) Mechanician Processes | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2016-12-31 | FPMSETA |
Core | 22772 | National Certificate: Mechatronics | Level 4 | Level TBA: Pre-2009 was L4 | Passed the End Date - Status was "Reregistered" |
2012-06-30 | MERSETA |
Elective | 58880 | Further Education and Training Certificate: Fluid Power | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | MERSETA |
Elective | 67649 | Further Education and Training Certificate: Mechatronics | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | MERSETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |