SAQA All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.
SOUTH AFRICAN QUALIFICATIONS AUTHORITY 
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: 

Fabricate, erect and strip steel and timber formwork for T-walls, decks and beams and single flight staircases 
SAQA US ID UNIT STANDARD TITLE
14224  Fabricate, erect and strip steel and timber formwork for T-walls, decks and beams and single flight staircases 
ORIGINATOR
SGB Building Construction 
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY
-  
FIELD SUBFIELD
Field 12 - Physical Planning and Construction Building Construction 
ABET BAND UNIT STANDARD TYPE PRE-2009 NQF LEVEL NQF LEVEL CREDITS
Undefined  Regular  Level 3  NQF Level 03  12 
REGISTRATION STATUS REGISTRATION START DATE REGISTRATION END DATE SAQA DECISION NUMBER
Passed the End Date -
Status was "Reregistered" 
2018-07-01  2023-06-30  SAQA 06120/18 
LAST DATE FOR ENROLMENT LAST DATE FOR ACHIEVEMENT
2024-06-30   2027-06-30  

In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise.  

This unit standard does not replace any other unit standard and is not replaced by any other unit standard. 

PURPOSE OF THE UNIT STANDARD 
Learners` who are assessed as competent against this unit standard will be able to fabricate, erect and strip steel and timber formwork for T-walls, decks, beams and single flight staircases in accordance with working drawing specifications, National Building Regulations and safety legislation ensuring that client requirements for cost-effective and quality products are met within the prescribed timeframes.The competencies contained in this unit standard complement the other carpentry competencies that make up this qualification and will contribute to the development of a professional community of Carpentry practitioners who are able to use Science and Technology responsibly and cost-effectively. It should result in improved quality and service delivery in Carpentry.This competence complements the other carpentry competencies and contributes to the development of a professional community of Carpentry practitioners, who are able to use Science and Technology responsibly and cost-effectively. It should result in improved quality and service delivery in Carpentry. The contribution to The National Skills Development Strategy is the key developmental interface between learners and new competencies to be achieved. 

LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING 
The learner has acquired the following competencies:
  • Use drawings and identify, use and maintain tools, machines, equipment and materials for construction carpentry site practice
  • Apply Health and Safety to a Work Area
  • Erect, Use and Dismantle Access Equipment
  • Set out and Prepare Construction Carpentry Work Areas
  • Fabricate, Erect and Strip Formwork for straight walls, columns and bases 

  • UNIT STANDARD RANGE 
  • Formwork is to be fabricated from steel or timber for a straight wall, column and base up to 2.4m, with vertical or horizontal joints
  • Steel or timber formwork is to be erected up to a height of 3m.
  • Support work materials relate to beams and decks only.
  • Cast-in items include weep hole pipes; holding down bolts and void formers
  • Assessment is to be carried out in normal climatic conditions. Fabrication in this context refers to the fabrication of formwork not in situ, i.e. on a simulated construction site. 

  • Specific Outcomes and Assessment Criteria: 

    SPECIFIC OUTCOME 1 
    Conduct planning activities associated with the fabrication of formwork. 
    OUTCOME NOTES 
    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Work activities are planned to facilitate productive workflow and compliance with working drawings. 

    ASSESSMENT CRITERION 2 
    2. All elements are correctly described in the plan to facilitate productive workflow, waste minimisation and compliance with working drawings. 
    ASSESSMENT CRITERION RANGE 
    Range of elements include type and quantities of materials, tools and equipment, plant, personnel, work sequence, time frames, plant handling, personnel, work sequences.
     

    ASSESSMENT CRITERION 3 
    3. The work area is checked and cleared of potential hazards. 

    ASSESSMENT CRITERION 4 
    4. Hazards that cannot be cleared are reported to the responsible authorities. 

    ASSESSMENT CRITERION 5 
    5. Tools, equipment and personal protective equipment required for the task are to hand and are confirmed to be in good working order. 

    ASSESSMENT CRITERION 6 
    6. Formwork profiles are correctly marked out in accordance with specified dimensions. 

    ASSESSMENT CRITERION 7 
    7. All instructions are comprehensively communicated and effectively carried out by support personnel. 

    ASSESSMENT CRITERION 8 
    8. Formwork materials are identified correctly and timeously requisitioned, received and prepared in readiness for construction. 

    SPECIFIC OUTCOME 2 
    Fabricate formwork and conduct post-fabrication activities 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. The formwork is fabricated in accordance with the safety requirements of the workplace. 

    ASSESSMENT CRITERION 2 
    2. Completed formwork is neat, straight and true to the specified dimensions and within the specified SABS tolerances. 

    ASSESSMENT CRITERION 3 
    3. All design specifications and instructions are carried out correctly. 

    ASSESSMENT CRITERION 4 
    4. All joints are grout-loss tight. 

    ASSESSMENT CRITERION 5 
    5. Formwork is fabricated and completed in accordance with work schedules. 

    ASSESSMENT CRITERION 6 
    6. Tools, equipment and personal protective equipment are correctly identified and used in accordance with health and safety legislation. 

    ASSESSMENT CRITERION 7 
    7. Materials wastage is within accepted industry limits. 

    ASSESSMENT CRITERION 8 
    8. The expertise of support personnel is considered and effectively utilised. 

    ASSESSMENT CRITERION 9 
    9. All instructions are comprehensively communicated and correctly executed by support personnel. 

    ASSESSMENT CRITERION 10 
    10. Formwork panels are correctly marked or numbered as instructed. 

    ASSESSMENT CRITERION 11 
    11. Compliance with issued instructions is checked and the correctness of markings or numbering is confirmed. 

    ASSESSMENT CRITERION 12 
    12. All work areas are cleared of debris and cleaned. 

    ASSESSMENT CRITERION 13 
    13. Tools and surplus materials are safely and securely stored. 

    ASSESSMENT CRITERION 14 
    14. Company procedures for reporting completed work to designated personnel are adhered to. 

    SPECIFIC OUTCOME 3 
    Conduct planning activities associated with the erection of support work and formwork. 
    OUTCOME NOTES 
    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Work activities are planned to facilitate productive workflow and compliance with working drawings. 

    ASSESSMENT CRITERION 2 
    2. All elements are correctly described in the plan to facilitate productive workflow, waste minimisation and compliance with working drawings. 

    ASSESSMENT CRITERION 3 
    3. Scaffolding is thoroughly checked and confirmed to be adequately constructed for the task in terms of size, position and in accordance with the requirements of the OHSA. 

    ASSESSMENT CRITERION 4 
    4. Any faults that are identified to the reinforcing and base are immediately reported to designated personnel. 

    ASSESSMENT CRITERION 5 
    5. The correct shuttering materials are identified, received, prepared for use and safely stacked at the work area in readiness for the task at hand. 

    ASSESSMENT CRITERION 6 
    6. Any shortages or damages are immediately reported to designated personnel. 

    SPECIFIC OUTCOME 4 
    Erect support work for beams and decks. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Work is carried out in accordance with the safety requirements of the workplace. 

    ASSESSMENT CRITERION 2 
    2. The support work for the foundation is verified and readiness for erection is confirmed by the designated personnel prior to the support work being erected. 

    ASSESSMENT CRITERION 3 
    3. Support work is erected in the correct position in accordance with the specified design and in accordance with instructions received. 

    ASSESSMENT CRITERION 4 
    4. An inspection is arranged with designated personnel for the support work to be checked and confirmed prior to the commencement of further work operations. 

    ASSESSMENT CRITERION 5 
    5. Personal protective equipment is correctly used and the requirements of the OHSA are adhered to. 

    ASSESSMENT CRITERION 6 
    6. The expertise of support personnel is considered and effectively utilised. 

    ASSESSMENT CRITERION 7 
    7. All instructions are comprehensively communicated and correctly executed by support personnel. 

    SPECIFIC OUTCOME 5 
    Erect formwork with cast-in items. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Work is carried out in accordance with the safety requirements of the workplace. 

    ASSESSMENT CRITERION 2 
    2. The erected formwork is neat, true to line, plumb and in accordance with specified dimensions and within the specified SABS tolerances. 

    ASSESSMENT CRITERION 3 
    3. Levels are transferred in accordance with SABS tolerances. 

    ASSESSMENT CRITERION 4 
    4. The erected formwork is grout-loss tight and stayed. 

    ASSESSMENT CRITERION 5 
    5. The erected formwork is firm and stable for the pouring of the concrete. 

    ASSESSMENT CRITERION 6 
    6. Formwork is erected and completed in accordance with work schedules. 

    ASSESSMENT CRITERION 7 
    7. Tools, equipment and personal protective equipment are correctly identified and used in accordance with health and safety legislation. 

    ASSESSMENT CRITERION 8 
    8. The expertise of support personnel is considered and effectively utilised. 

    ASSESSMENT CRITERION 9 
    9. All instructions are comprehensively communicated and correctly executed by support personnel. 

    ASSESSMENT CRITERION 10 
    10. The erected formwork is checked on completion and compliance with issued instructions is confirmed. 

    SPECIFIC OUTCOME 6 
    Strip formwork and support work 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Formwork and support work is stripped in accordance with specified curing and production requirements. 

    ASSESSMENT CRITERION 2 
    2. Appropriate precautions are taken to minimise the risk of damage to the structure, equipment and materials and ensure the safety of self and personnel during the stripping process. 

    ASSESSMENT CRITERION 3 
    3. Personal protective equipment is used in accordance with the requirements of the OHSA. 

    ASSESSMENT CRITERION 4 
    4. All materials are cleaned, oiled and stacked in accordance with accepted industry standards. 

    ASSESSMENT CRITERION 5 
    5. All instructions are comprehensively communicated and correctly executed by support personnel. 

    ASSESSMENT CRITERION 6 
    6. Formwork is completely stripped within the specified timeframes. 


    UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS 
  • Anyone assessing a learner or moderating the assessment of a learner against this unit standard must be registered as an assessor with the CETA - ETQA, for this unit standard.
  • Any institution offering learning that will enable the achievement of this unit standard must be accredited as a provider with the CETA - ETQA
  • CETA - ETQA is responsible for moderation of learner achievements for Learners` who meet the requirements of this qualification. 

  • UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE 
  • Techniques for transferring levels in accordance with SABS tolerances
  • SABS tolerances for steel or timber formwork up to 2.4m with vertical or horizontal joints
  • The relationship between pressure exerted by concrete and the height of structures and the impact of this on the spacing of through ties, clamps and walers
  • Industry workmanship standards and their impact on production, cost, safety and quality of finish to product
  • Occupational Health and Safety Act (OHSA). 

  • UNIT STANDARD DEVELOPMENTAL OUTCOME 
    N/A 

    UNIT STANDARD LINKAGES 
    N/A 


    Critical Cross-field Outcomes (CCFO): 

    UNIT STANDARD CCFO IDENTIFYING 
    Identify and solve problems. This relates to the following specific outcomes and its relevant assessment criteria:

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated.

    Assessment criteria:
  • The work area is checked and cleared of potential hazards
  • Hazards that can not be cleared are reported to the responsible authorities

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • All design specifications and instructions are carried out correctly
  • Compliance with issued instructions is checked and the correctness of markings or numbering is confirmed

    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected

    Assessment criteria:
  • Scaffolding is thoroughly checked and confirmed to be adequately constructed for the task in terms of size, position and in accordance with the requirements of the OHSA
  • Any faults that are identified to the reinforcing and base are immediately reported to designated personnel
    Range of faults is limited to loose and missing ties, inadequate cover to reinforcing and uneven spacing of bars.

    Erect support work for beams and decks

    Assessment criteria:
  • Work is carried out in accordance with the safety requirements of the workplace
  • Support work is erected in the correct position in accordance with the specified design and in accordance with instructions received

    Strip formwork and support work

    Assessment criteria:
  • Appropriate precautions are taken to minimise the risk of damage to the structure, equipment and materials and ensure the safety of self and personnel during the stripping process. 

  • UNIT STANDARD CCFO WORKING 
    Work effectively with others as a member of a team. This relates to the following specific outcomes and its assessment criteria.

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated

    Assessment criteria:
  • Formwork materials are identified, correctly and timeously requisitioned, received and prepared in readiness for construction

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • The expertise of support personnel is considered and effectively utilised
  • Compliance with issued instructions is checked and the correctness of markings or numbering is confirmed
  • Company procedures for reporting completed work to designated personnel are adhered

    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected

    Assessment criteria:
  • Any faults that are identified to the reinforcing and base are immediately reported to designated personnel
    Range of faults is limited to loose and missing ties, inadequate cover to reinforcing and uneven spacing of bars
  • Any shortages or damages are immediately reported to designated personnel
    Range of preparation includes the cleaning and treating of shutters

    Erect support work for beams and decks

    Assessment criteria:
  • The support work for the foundation is verified and readiness for erection is confirmed by the designated personnel prior to the support work being erected
  • An inspection is arranged with designated personnel for the support work to be checked and confirmed prior to the commencement of further work operations
  • The expertise of support personnel is considered and effectively utilised

    Erect formwork with cast-in items

    Assessment criteria:
  • The expertise of support personnel is considered and effectively utilised

    Strip formwork and support work

    Assessment criteria:
  • Appropriate precautions are taken to minimise the risk of damage to the structure, equipment and materials and ensure the safety of self and personnel during the stripping process. 

  • UNIT STANDARD CCFO ORGANISING 
    Organise and manage oneself and one`s activities responsible and effectively. This relates to the following specific outcomes:

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated

    Assessment criteria:
  • Work activities are planned to facilitate productive workflow and compliance with working drawings
  • Tools, equipment and personal protective equipment required for the task are to hand and are confirmed to be in good working order
  • Formwork materials are identified correctly and timeously requisitioned, received and prepared in readiness for construction

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • Formwork is fabricated and completed in accordance with work schedules
  • Materials wastage is within accepted industry limits
  • Formwork panels are correctly marked or numbered as instructed
  • All work areas are cleared of debris and cleaned
  • Tools and surplus materials are safely and securely stored

    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected

    Assessment criteria:
  • The correct shuttering materials are identified, received, prepared for use and safely stacked at the work area in readiness for the task at hand

    Erect support work for beams and decks

    Assessment criteria:
  • Personal protective equipment is correctly used and the requirements of the OHSA are adhered to.

    Erect formwork with cast-in items

    Assessment criteria:
  • Formwork is erected and completed in accordance with work schedules

    Strip formwork and support work

    Assessment criteria:
  • Personal protective equipment is used in accordance with the requirements of the OHSA Act
  • All materials are cleaned, oiled and stacked in accordance with accepted industry standards. 

  • UNIT STANDARD CCFO COLLECTING 
    Collect, analyse, organise and critically evaluate information. This relates to the following specific outcomes and its relevant assessment:

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated

    Assessment criteria:
  • Work activities are planned to facilitate productive workflow and compliance with working drawings
  • All elements are correctly described in the plan to facilitate productive workflow, waste minimisation and compliance with working drawings
    Range of elements include type and quantities of materials, tools and equipment, plant, personnel, work sequence, time frames, plant handling, personnel, work sequences
  • Formwork profiles are correctly marked out in accordance with specified dimensions

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • All design specifications and instructions are carried out correctly
  • Formwork panels are correctly marked or numbered as instructed

    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected.

    Assessment criteria:
  • Scaffolding is thoroughly checked and confirmed to be adequately constructed for the task in terms of size, position and in accordance with the requirements of the OHSA

    Erect support work for beams and decks

    Assessment criteria:
  • Support work is erected in the correct position in accordance with the specified design and in accordance with instructions received

    Erect formwork with cast-in items

    Assessment criteria:
  • Work is carried out in accordance with the safety requirements of the workplace

    Strip formwork and support work

    Assessment criteria:
  • Formwork and support work is stripped in accordance with specified curing and production requirements. 

  • UNIT STANDARD CCFO COMMUNICATING 
    Communicate effectively using visual, mathematical and/or language skills. This relates to the following specific outcomes and their relevant assessments.

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated

    Assessment criteria:
  • Hazards that cannot be cleared are reported to the responsible authorities
  • All instructions are comprehensively communicated and effectively carried out by support personnel

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • All instructions are comprehensively communicated and correctly executed by support personnel
  • Company procedures for reporting completed work to designated personnel are adhered to

    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected

    Assessment criteria:
  • Any faults that are identified to the reinforcing and base are immediately reported to designated personnel
    Range of faults is limited to loose and missing ties, inadequate cover to reinforcing and uneven spacing of bars
  • Any shortages or damages are immediately reported to designated personnel

    Erect support work for beams and decks

    Assessment criteria:
  • An inspection is arranged with designated personnel for the support work to be checked and confirmed prior to the commencement of further work operations
  • All instructions are comprehensively communicated and correctly executed by support personnel

    Erect formwork with cast-in items

    Assessment criteria:
  • All instructions are comprehensively communicated and correctly executed by support personnel

    Strip formwork and support work

    Assessment criteria:
  • All instructions are comprehensively communicated and correctly executed by support personnel. 

  • UNIT STANDARD CCFO SCIENCE 
    Use science and technology effectively and critically. This relates to the following specific outcomes and its relevant assessment:

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated

    Assessment criteria:
  • Formwork materials are identified, correctly and timeously requisitioned, received and prepared in readiness for construction

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • Tools, equipment and personal protective equipment are correctly identified and used in accordance with health and safety legislation

    Erect support work for beams and decks

    Assessment criteria:
  • Support work is erected in the correct position in accordance with the specified design and in accordance with instructions received
  • Personal protective equipment is correctly used and the requirements of the OHSA are adhered to

    Erect formwork with cast-in items

    Assessment criteria:
  • The erected formwork is firm and stable for the pouring of the concrete
  • Tools, equipment and personal protective equipment are correctly identified and used in accordance with health and safety legislation
  • Levels are transferred in accordance with SABS tolerances

    Strip formwork and support work

    Assessment criteria:
  • Personal protective equipment is used in accordance with the requirements of the OHSA. 

  • UNIT STANDARD CCFO DEMONSTRATING 
    Understand the world as a set of related systems. This relates to the following specific outcomes and its relevant assessment:

    Conduct planning activities associated with the fabrication of formwork and prepare the work area where the formwork is to be fabricated

    Assessment criteria:
  • Hazards that cannot be cleared are reported to the responsible authorities
  • Formwork materials are identified, correctly and timeously requisitioned, received and prepared in readiness for construction

    Fabricate formwork and conduct post-fabrication activities

    Assessment criteria:
  • Completed formwork is neat, straight and true to the specified dimensions and within the specified SABS tolerances
  • All joints are grout-loss tight
  • Tools, equipment and personal protective equipment are correctly identified and used in accordance with health and safety legislation
  • Materials wastage is within accepted industry limits
  • All work areas are cleared of debris and cleaned
  • Tools and surplus materials are safely and securely stored

    Conduct planning activities associated with the erection of support work and formwork and prepare the work area where the support work and formwork is to be erected

    Assessment criteria:
  • The correct shuttering materials are identified, received, prepared for use and safely stacked at the work area in readiness for the task at hand
    Range of preparation includes the cleaning and treating of shutters
  • Any shortages or damages are immediately reported to designated personnel

    Erect support work for beams and decks

    Assessment criteria:
  • Work is carried out in accordance with the safety requirements of the workplace
  • The support work for the foundation is verified and readiness for erection is confirmed by the designated personnel prior to the support work being erected
  • An inspection is arranged with designated personnel for the support work to be checked and confirmed prior to the commencement of further work operations
  • The expertise of support personnel is considered and effectively utilised

    Erect formwork with cast-in items

    Assessment criteria:
  • Work is carried out in accordance with the safety requirements of the workplace
  • The erected formwork is neat, true to line, plumb and in accordance with specified dimensions and within the specified SABS tolerances
  • The erected formwork is grout-loss tight and stayed
  • The erected formwork is firm and stable for the pouring of the concrete

    Strip formwork and support work

    Assessment criteria:
  • Appropriate precautions are taken to minimise the risk of damage to the structure, equipment and materials and ensure the safety of self and personnel during the stripping process
  • All materials are cleaned, oiled and stacked in accordance with accepted industry standards. 

  • UNIT STANDARD ASSESSOR CRITERIA 
    N/A 

    REREGISTRATION HISTORY 
    As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. 

    UNIT STANDARD NOTES 
    Fabrication of steel or timber formwork:Instructions given by the assessor to learners for the fabrication of steel or timber formwork are informed by the requirements of SABS 1200 (SABS Tolerances are 1200G, Column 2). 

    QUALIFICATIONS UTILISING THIS UNIT STANDARD: 
      ID QUALIFICATION TITLE PRE-2009 NQF LEVEL NQF LEVEL STATUS END DATE PRIMARY OR DELEGATED QA FUNCTIONARY
    Core  22670   National Certificate: Construction Carpentry  Level 3  NQF Level 03  Passed the End Date -
    Status was "Reregistered" 
    2009-03-12  Was CETA until Last Date for Achievement 
    Elective  65409   National Certificate: Building and Civil Construction  Level 3  NQF Level 03  Passed the End Date -
    Status was "Reregistered" 
    2023-06-30  CETA 


    PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: 
    This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here.
     
    1. Akaf Bodyguards 
    2. Artisan Development Academy 
    3. BELCOMEC TRAINING 
    4. Better Best Agri Development 
    5. BH Training and Consulting (Pty) Ltd 
    6. Bhekuza Training Centre 
    7. Bhekwell Group 
    8. Big Tree Group 
    9. BOLAND COLLEGE (Paarl) 
    10. Border Kei Training Trust 
    11. Bright Storm Projects 
    12. CBM Training 
    13. CENTRE FOR CAREER GUIDANCE AND PROFESSIONAL DEVELOPMENT CC 
    14. Certified Training Solutions (Pty) Ltd 
    15. Construction Resource Development College 
    16. Eastcape Training Centre 
    17. Edu House South Africa 
    18. Ekurhuleni Artisans and Skills Training Pty Ltd 
    19. Elangeni College for FET - Central Office 
    20. Goitsebasadi Construction Project 
    21. Goldfields FET College 
    22. Ikemeleng Training and Development Services 
    23. In Touch Community Development & Project Managers 
    24. INDUSTRIES EDUCATION & TRAINING INSTITUTE 
    25. IZWE TRAINING AND DEVELOPMENT 
    26. Josmap Training Institute 
    27. L S Nkosi CC 
    28. Leps Training Consultants 
    29. Madzahisi College 
    30. Mahumani Empowerment Servives Centre 
    31. Majoncor Projects and Training Academy (Pty) Ltd 
    32. Majuba TVET College 
    33. Masana Social Consultants cc 
    34. Mavco Engineering 
    35. Microzone Training CC 
    36. Mnambithi TVET College 
    37. Motheo TVET College 
    38. MPUMALANGA REGIONAL TRAINING TRUST 
    39. Mthoms Trading 
    40. MTL Training and Projects 
    41. Nokuthula Dube & Associates 
    42. NOMAKU TRADERS CC 
    43. Northern Cape Rural TVET College 
    44. Northlink TVET College 
    45. Primeserv Corporate Solutions 
    46. Protech Training (Pty) Ltd 
    47. Qualfurn Training & Projects (Pty) Ltd 
    48. Ratidzo Trading PTY Ltd 
    49. Raubex Construction Pty (Ltd) 
    50. Sakhisizwe Development Training 
    51. Sekhukhune District Municipality EMS Training Academy 
    52. Sheq and Environmental Projects 
    53. Sonani Training and Communications 
    54. Stefanutti Stocks Holding Limited 
    55. Tjeka Training Matters Pty Ltd 
    56. Tovani Traiding 299 
    57. Training Force (Pty) Ltd 
    58. Tshwane North College for FET - Central Office 
    59. Ubucubu Home Industries 
    60. Zama Training & Developments 



    All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.