All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install bulkheads |
SAQA US ID | UNIT STANDARD TITLE | |||
243749 | Install bulkheads | |||
ORIGINATOR | ||||
SGB Building Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Building Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 6 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
Qualifying learners are capable of installing a range of bulkheads, while applying prescribed safety and best practice good housekeeping standards and norms which will contribute towards the overall efficiency of their organisations and ensure that breakages and work stoppages are kept to a minimum.
This competence also advances a learner's personal expertise and employability in the construction sector and related fields, for example interior design and refurbishment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
It is assumed that learners are already competent in the following:
|
UNIT STANDARD RANGE |
N/A |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Install a basic bulkhead. |
OUTCOME RANGE |
Finishes include wallpaper, laminating and tiles, painting and bonding liquids. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Floor protection is laid down to give total coverage. |
ASSESSMENT CRITERION 2 |
Materials and tools are laid out in a logical fashion. |
ASSESSMENT CRITERION 3 |
Scaffolding and support mechanisms are prepared safely. |
ASSESSMENT CRITERION 4 |
Framework is installed according to engineer's design. |
ASSESSMENT CRITERION 5 |
Boards are installed onto framework considering correct bending practice. |
ASSESSMENT CRITERION 6 |
Jointing/skimming is performed as required. |
ASSESSMENT CRITERION 7 |
The required finish for decoration is applied according to requirements. |
ASSESSMENT CRITERION 8 |
Rubbish is removed from installation site. |
ASSESSMENT CRITERION 9 |
The installation site is cleaned to restore it to its original condition. |
ASSESSMENT CRITERION 10 |
Tools are cleaned as per required standards. |
ASSESSMENT CRITERION 11 |
Tool inventory is completed before handover is conducted. |
ASSESSMENT CRITERION 12 |
Site acceptance, snagging and handover are conducted as per standard procedures. |
SPECIFIC OUTCOME 2 |
Install an advanced bulkhead. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Floor protection is laid down to give total coverage. |
ASSESSMENT CRITERION 2 |
Materials and tools are laid out in a logical fashion. |
ASSESSMENT CRITERION 3 |
Scaffolding and support mechanisms are prepared in accordance with procedures. |
ASSESSMENT CRITERION 4 |
Framework is installed according to engineer's design. |
ASSESSMENT CRITERION 5 |
Boards are installed onto framework considering correct bending practice. |
ASSESSMENT CRITERION 6 |
Jointing/skimming is performed as required. |
ASSESSMENT CRITERION 7 |
The required finish for decoration is applied. |
ASSESSMENT CRITERION 8 |
Rubbish is removed from installation site. |
ASSESSMENT CRITERION 9 |
The installation site is cleaned to re-establish its original clean condition. |
ASSESSMENT CRITERION 10 |
Tools are cleaned as per required standards. |
ASSESSMENT CRITERION 11 |
Tool inventory is completed before handover is conducted. |
ASSESSMENT CRITERION 12 |
Site acceptance, snagging and handover are correctly conducted. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Qualifying learners understand and are competent to explain how to:
> A basic bulkhead. > An advanced bulkhead. > Prescribed safety procedures. > Best practice housekeeping standards and norms. |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems by taking responsible decisions, thereby demonstrating critical evaluation and creative thinking, and applying knowledge of basic and advanced bulkhead installation to select appropriate products for use in specified situations and ensuring adherence to best practice industry/housekeeping standards and norms. |
UNIT STANDARD CCFO WORKING |
Work effectively as a member of a team for example, by physically handling/fixing/installing when installing a basic- and an advanced bulkhead with the assistance of other team members. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage themselves and their own activities responsibly and effectively by correctly installing a basic- and an advanced bulkhead, in an organised manner. |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information by adhering to best practice prescribed housekeeping standards and norms on the installation site. |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate awareness that problem-solving contexts do not exist in isolation by recognising and understanding that the:
|
UNIT STANDARD CCFO CONTRIBUTING |
Contribute to their own full development and the social and economic development of society at large. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
N/A |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 58247 | National Certificate: Ceiling and Partitioning Installation | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |