All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Perform work using a project approach |
SAQA US ID | UNIT STANDARD TITLE | |||
244563 | Perform work using a project approach | |||
ORIGINATOR | ||||
SGB Project Management | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 03 - Business, Commerce and Management Studies | Project Management | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 8 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
The person credited with this unit standard is able to use a project approach for simple situations that can be treated as a project through developing and agreeing the project purpose, deliverables and timeframe, developing a simple plan, controlling the work and closing the project.
The qualifying learner is capable of: |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The learner must be competent in:
|
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Demonstrate an understanding of applying a project approach. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The project concept is explained with examples of project occurrences. |
ASSESSMENT CRITERION 2 |
The key characteristics of a project are explained with practical examples. |
ASSESSMENT CRITERION 3 |
The key steps for applying a project approach are described with examples. |
SPECIFIC OUTCOME 2 |
Determine and agree an approach to be taken for a small, simple project. |
OUTCOME RANGE |
Project in this standard may include but is not limited to an event such as a school dance, or a party, or a wedding, or a year end exhibition, or a simple research project, or achieving a personal goal, or community project such as fund raising or establishing a vegetable garden. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Parties interested in the project are identified and their interest described and recorded in a clear and concise manner. |
ASSESSMENT CRITERION 2 |
Project purpose is determined, documented and agreed with project sponsor and/or beneficiary. |
ASSESSMENT CRITERION RANGE |
ASSESSMENT CRITERION 3 |
Discussions are held with key parties to define and agree situation and approach to a project. |
ASSESSMENT CRITERION 4 |
Preliminary ideas for approach to the project are documented and agreed with key parties. |
SPECIFIC OUTCOME 3 |
Prepare a project plan of action. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The major deliverables and associated activities are identified, described and recorded in a clear manner. |
ASSESSMENT CRITERION 2 |
Simple sequence of the activities or tasks for the project is developed, recorded and reflects the order in which the work must be done to produce the deliverables. |
ASSESSMENT CRITERION 3 |
Time estimates for each activity or task are developed and recorded with the task information. |
ASSESSMENT CRITERION 4 |
Resource types and quantities required for each activity or task are identified, clearly described and recorded with the task information. |
ASSESSMENT CRITERION 5 |
Costs for each resource type are sourced and total cost per task is calculated and recorded with the task information. |
ASSESSMENT CRITERION NOTES |
Some resource types may have a zero cost. |
ASSESSMENT CRITERION 6 |
Simple cost budget is produced for the project that includes and summarises all resource and task costs. |
ASSESSMENT CRITERION RANGE |
Cost budget should show the forecast expenditure against an agreed time period. |
ASSESSMENT CRITERION 7 |
Simple project plan is produced recording all agreements for the project. |
ASSESSMENT CRITERION RANGE |
Project plan may include but is not limited to purpose, major deliverables, simple calendar or schedule of tasks, cost budget and roles and responsibilities. |
SPECIFIC OUTCOME 4 |
Undertake project activities. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Activities or tasks are allocated to team members in accordance with plan of action. |
ASSESSMENT CRITERION 2 |
Activities or tasks are undertaken in accordance with schedule. |
ASSESSMENT CRITERION 3 |
Progress on activities or tasks is communicated to interested parties. |
ASSESSMENT CRITERION 4 |
Financial data is presented in required format. |
SPECIFIC OUTCOME 5 |
Check and communicate progress of a project. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Progress on activities, deliverables and expenditure is regularly tracked and progress checked against project plan. |
ASSESSMENT CRITERION 2 |
Differences between actual and planned activities, deliverables or expenses are identified and the causes described. |
ASSESSMENT CRITERION 3 |
Changes and their impact on deliverables, work or costs are identified and described in a report. |
ASSESSMENT CRITERION 4 |
Problems are identified and solutions or corrective action developed with the team. |
ASSESSMENT CRITERION 5 |
Corrective action is implemented as agreed with the project team and/or project sponsor. |
ASSESSMENT CRITERION 6 |
All project deliverables are complete and accepted by project sponsor. |
ASSESSMENT CRITERION 7 |
Completion of the project is communicated to interested parties. |
ASSESSMENT CRITERION 8 |
Lessons from the project are developed with the team and recorded for future reference. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
This standard expects a simple level of understanding and application of project management principles, processes and techniques:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems pertaining to the project activities. |
UNIT STANDARD CCFO WORKING |
Work effectively with others in the process of monitoring and controlling the cost management plan. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage oneself and ones activities in such a way so as to balance project work with time available and priority of tasks. |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information related to the project activities. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively with relevant parties regarding purpose, proposed activities and progress of the project. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
A project is seen to be a focussed once off or unique set of activities to produce a deliverable, service or event.
A project approach is seen to be the adoption of project management processes and techniques in a simplistic manner to achieve results. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 65010 | National Certificate: Aviation Support Operations | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2018-06-30 | TETA |
Elective | 58800 | Further Education and Training Certificate: Project Support Services | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | SERVICES |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |