All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Construct, maintain and dismantle Low Voltage overhead networks |
SAQA US ID | UNIT STANDARD TITLE | |||
258936 | Construct, maintain and dismantle Low Voltage overhead networks | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 10 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the electrical Low Voltage reticulation environment.
A person credited with this unit standard will be able to do the following on Low Voltage reticulation networks: This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical construction- and distribution environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
Learning assumed to be in place and Recognition of Prior Learning (RPL):
The following knowledge, skills attitude and/or equivalent: |
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan and prepare to construct, maintain and dismantle Low Voltage networks. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job instructions are obtained and the section of electrical network to be constructed/maintained/dismantled is identified according to geographical/electrical network diagrams. |
ASSESSMENT CRITERION 2 |
The scope of work is interpreted and a sequence of operation is planned according to construction, maintenance and dismantling procedures. |
ASSESSMENT CRITERION 3 |
Isolation and earthing of the affected section of the network is arranged and work permits received according to operating regulations, job instructions/maintenance schedules or breakdown reports where applicable. |
ASSESSMENT CRITERION 4 |
Appropriate tools, material and equipment are identified, selected and checked for functionality to meet the requirements of the task and according to job and statutory requirements. |
SPECIFIC OUTCOME 2 |
Construct Low Voltage networks. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job instructions are received for the construction of the relevant new section of the network according to construction regulations, standards and procedures. |
ASSESSMENT CRITERION 2 |
The required electrical hardware and equipment is checked for availability and conformance to job specifications, requirements and quality standards. |
ASSESSMENT CRITERION 3 |
The electrical hardware and equipment is constructed according to applicable procedures or manufacturer's specifications. |
ASSESSMENT CRITERION 4 |
The newly constructed electrical installation is inspected and tested to ensure that it is operational according to pre-commissioning requirements. |
ASSESSMENT CRITERION 5 |
The necessary documentation is completed and submitted according to the pre-commissioning and hand-over procedures. |
SPECIFIC OUTCOME 3 |
Inspect, maintain and repair Low Voltage networks. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Ensure that the affected section of the electrical reticulation network was isolated, earthed and work permit/worker's register was received for the affected section of the network according to operating procedures where necessary. |
ASSESSMENT CRITERION 2 |
The work site conditions and affected electrical hardware/equipment are assessed for possible safety risks and preventative measures implemented according to safety risk assessment procedures. |
ASSESSMENT CRITERION 3 |
The affected section of the electrical reticulation network is visually inspected prior to maintenance and repairs according to prescribed fault finding procedures. |
ASSESSMENT CRITERION 4 |
The electrical hardware and equipment is maintained, repaired or replaced according to applicable maintenance procedures or manufacturer's specifications. |
ASSESSMENT CRITERION 5 |
The maintained or replaced electrical hardware and equipment is inspected and tested to ensure that it is operational according to manufacturer's requirements. |
ASSESSMENT CRITERION 6 |
Safety precautions/procedures are followed before, during and after inspection and maintenance of the overhead line or equipment. |
SPECIFIC OUTCOME 4 |
Dismantle Low Voltage networks. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job instructions are received for the dismantling of the relevant section of the network according to relevant standards and procedures. |
ASSESSMENT CRITERION 2 |
The work site conditions and affected electrical hardware/equipment are assessed for possible safety risks and preventative measures implemented prior to dismantling according to safety risk assessment procedures. |
ASSESSMENT CRITERION 3 |
The electrical hardware and equipment is dismantled according to applicable procedures. |
ASSESSMENT CRITERION 4 |
The necessary documentation was completed and submitted according to the dismantling procedures. |
SPECIFIC OUTCOME 5 |
Complete the work task. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Work area is restored to serviceable condition according to statutory requirements. |
ASSESSMENT CRITERION 2 |
Completion of job is communicated, permit/worker's register cleared where necessary according to local reporting and operating procedures. |
ASSESSMENT CRITERION 3 |
Ensure that the replaced, dismantled or excess hardware and equipment has been returned to the stores. |
ASSESSMENT CRITERION 4 |
Appropriate tools and safety equipment are cleaned and stored according to statutory requirements. |
ASSESSMENT CRITERION 5 |
Documentation is completed accurately according to work site procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identifying and solving problems in which responsible decisions have been made regarding the maintenance/replacement of electrical line hardware/equipment action. |
UNIT STANDARD CCFO WORKING |
Work effectively with others as members of a team, group, organisation or community:
|
UNIT STANDARD CCFO ORGANISING |
Organise and manage themselves and their activities responsibly and effectively:
|
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information:
|
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively:
|
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate an understanding of the world as a set of related systems:
|
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Notes to Assessors:
Assessors should keep the following principles in mind when designing and conducting assessments against this unit standard: |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 73313 | National Certificate: Electrical Engineering | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | 4 TOPS ACADEMY |
2. | Better Best Agri Development |
3. | Double ST Training and Skills Development |
4. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
5. | Goitsebasadi Construction Project |
6. | KP ACADEMY (PTY) LTD |
7. | MSC ARTISAN ACADEMY |
8. | PCD College cc |
9. | POWER SYSTEMS TRAINING, CAPE TOWN |
10. | Protech Training (Pty) Ltd |
11. | Umfolozi FET College |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |