All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Manage construction project administration |
SAQA US ID | UNIT STANDARD TITLE | |||
263007 | Manage construction project administration | |||
ORIGINATOR | ||||
SGB Civil Engineering Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Physical Planning, Design and Management | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 5 | Level TBA: Pre-2009 was L5 | 6 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
15146 | Manage construction project administration | Level 5 | Level TBA: Pre-2009 was L5 | 8 |
PURPOSE OF THE UNIT STANDARD |
Learners who are assessed as competent against this unit standard will be able to develop and implement project, personnel and reporting administration. These competencies complement the other core management competencies and contribute to the development of a professional community of Civil Engineering Construction Managers.
The qualifying learner will be capable of: |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
UNIT STANDARD RANGE |
N/A |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Develop and implement reporting systems on a construction project. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Reporting systems are developed in accordance with company procedures and in conjunction with senior management. |
ASSESSMENT CRITERION 2 |
Data for reports are sourced and verified in accordance with project requirements and organizational procedures. |
ASSESSMENT CRITERION 3 |
Reports are compiled in accordance with the prescribed format. |
ASSESSMENT CRITERION 4 |
Reports are submitted in accordance with prescribed deadlines and organizational procedures. |
SPECIFIC OUTCOME 2 |
Monitor implementation of project record keeping and personnel administration. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Records are maintained in accordance with site procedures and quality management systems. |
ASSESSMENT CRITERION RANGE |
Site records include, but are not limited to:
|
ASSESSMENT CRITERION 2 |
Data is retrieved and provided in the form and manner appropriate to the needs of recipients. |
ASSESSMENT CRITERION 3 |
Personnel administration is implemented in accordance with site, quality and H.R. procedures and requirements. |
ASSESSMENT CRITERION RANGE |
Personnel administration includes, but is not limited to:
|
SPECIFIC OUTCOME 3 |
Measure and calculate quantities and produce payment certificates. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Actual quantities of work completed and accepted are calculated according to specifications. |
ASSESSMENT CRITERION 2 |
Measurements and calculations of quantities are made and reflected according to quantity surveying techniques and format. |
ASSESSMENT CRITERION 3 |
Payment certificates and invoices are produced according to company procedures and client requirements. |
SPECIFIC OUTCOME 4 |
Prepare and conduct meetings. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Notification, agenda and information for meetings are timeously produced and distributed. |
ASSESSMENT CRITERION 2 |
Meetings are conducted and minuted in accordance with accepted meeting procedures. |
ASSESSMENT CRITERION RANGE |
Meetings include, but is not limited to:
|
ASSESSMENT CRITERION 3 |
Feedback from meetings are given to team members and other relevant parties according to meeting outcomes. |
ASSESSMENT CRITERION 4 |
Follow up actions subsequent to meetings are implemented according to meeting outcomes. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
The qualifying learner will be able to understand and explain relevant aspects of the following:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems related to developing and implementing administration systems on a civil engineering construction project in which responses display that critical thinking is used for responsible decision making. |
UNIT STANDARD CCFO WORKING |
Work effectively with others as a member of a construction team to plan, implement and monitor civil engineering construction project administration. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage oneself and one's activities responsibly and effectively in the management of civil engineering construction administration. |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information about civil engineering construction to manage the administration of the project. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively using appropriate modes of oral and/or written persuasion in dealing with all civil engineering construction team members and management to develop, implement and monitor administration of a project. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard 15146, "Manage construction project administration", Level 5, 8 credits. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 66089 | National Certificate: Human Settlements Development | Level 5 | Level TBA: Pre-2009 was L5 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |