All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Implement site administration procedures on a construction project |
SAQA US ID | UNIT STANDARD TITLE | |||
9987 | Implement site administration procedures on a construction project | |||
ORIGINATOR | ||||
SGB Building Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Building Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 10 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
The purpose of this Unit Standard is to enable Construction Contractors to implement site administrative systems and procedures on a construction project. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
FETC NQF Level 2 literacy and numeracy competencies. |
UNIT STANDARD RANGE |
1. Creditors include those supplying materials, plant and equipment hire, and fuels.
2. Procurement processes include the use of requisitions, orders, delivery notes, invoices and statements. 3. Reconciliation of creditors payments includes delivery notes, invoices and statements. 4. Measurement of work includes for "Materials on Site" and "work-in-progress". 5. Stock control includes: stock-taking, reconciliation of stores received, issued and on-hand, and includes all materials, plant and equipment, consumables and fuels. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Implement a Drawing control system. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. A drawing register is implemented and maintained. |
ASSESSMENT CRITERION 2 |
2. A drawing revision control system is implemented. |
SPECIFIC OUTCOME 2 |
Apply an invoicing procedure. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Measurement of completed work is performed. |
ASSESSMENT CRITERION 2 |
2. Interim payment certificates (invoices) are produced in the correct format. |
ASSESSMENT CRITERION 3 |
3. Payment of certificates by the Client is monitored. |
SPECIFIC OUTCOME 3 |
Apply a site filing system. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Information and data is distributed. |
ASSESSMENT CRITERION 2 |
2. A project filing system is implemented and maintained. |
ASSESSMENT CRITERION 3 |
3. Record-keeping systems are implemented. |
SPECIFIC OUTCOME 4 |
Apply payment of creditors procedures. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Creditors are paid. |
ASSESSMENT CRITERION 2 |
2. Procurement processes are implemented. |
ASSESSMENT CRITERION 3 |
3. Creditors payments are reconciled. |
ASSESSMENT CRITERION 4 |
4. Stock control procedures are implemented. |
SPECIFIC OUTCOME 5 |
Conduct construction site meetings. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Client, management, and site meetings are conducted. |
ASSESSMENT CRITERION 2 |
2. Agendas and minutes of meetings are produced. |
ASSESSMENT CRITERION 3 |
3. Meeting attendees are notified of meetings. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
Assessment of learner achievements takes place at providers accredited by CETA (RSA, 1998b) for the provision of programs that result in the outcomes specified for the Certificate in Construction Contracting. CETA is responsible for moderation of learner achievements of learners who meet the requirements of this unit standard. |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Qualifying learners understand and can explain:
1. The concepts of Creditors and Debtors. 2. Drawing numbering and revision systems. 3. Measurement of pay items according to pay item descriptions. |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO WORKING |
Work effectively with others
1. Conduct construction site meetings. |
UNIT STANDARD CCFO COLLECTING |
Manage information
1. Implement a Drawing control system. 2. Apply an invoicing procedure. 3. Apply a site filing system. 4. Apply payment of creditors procedures. 5. Conduct construction site meetings. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively
1. Apply a site filing system. 2. Conduct construction site meetings. |
UNIT STANDARD CCFO SCIENCE |
Understand Contextual world-systems
1. Apply payment of creditors procedures. |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate scientific and technological competence
1. Apply payment of creditors procedures. |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 20813 | National Certificate: Construction Contracting | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | Abasizi Contractor Development Services Pty Ltd |
2. | Academy for Construction Skills (Pty) Ltd (ACS) |
3. | Akaf Bodyguards |
4. | ALLINA FRANCIS (SA) |
5. | Aveng Grinaker -LTA Civil Engineering |
6. | AVUXENI COMPUTER ACADEMY KZN |
7. | Bright Storm Projects |
8. | Capricorn FET College - Central Office |
9. | Construction Resource Development College |
10. | Double ST Training and Skills Development |
11. | Eastcape Training Centre |
12. | ENTELEKEY GROUP |
13. | Ikemeleng Training and Development Services |
14. | In Touch Community Development & Project Managers |
15. | Mahumani Empowerment Servives Centre |
16. | Masana Social Consultants cc |
17. | Mavco Engineering |
18. | Microzone Training CC |
19. | MOLOKO SMALL ENTERPRISE |
20. | Motheo Academy PTY LTD |
21. | Nkqubela Community Developers |
22. | Northlink TVET College |
23. | Novi General Services |
24. | Protech Training (Pty) Ltd |
25. | RUTHEKHO TRAINING ACADEMY (PTY) LTD |
26. | Sakhisizwe Development Training |
27. | SEDA Construction Incubator Trust |
28. | Somvi General Services |
29. | South African Value Education (Pty) Ltd |
30. | Tjeka Training Matters Pty Ltd |
31. | Tovani Traiding 299 |
32. | TSK Projects(PTY)LTD |
33. | Zama Training & Development cc |
34. | Zibuyile Consulting and Projects (Pty) Ltd |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |