All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Plan, organise and control pre - cast concrete manufacturing processes |
SAQA US ID | UNIT STANDARD TITLE | |||
116689 | Plan, organise and control pre - cast concrete manufacturing processes | |||
ORIGINATOR | ||||
SGB Civil Engineering Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Civil Engineering Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 10 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
The qualifying learner is capable of:
Integrating knowledge and understanding of materials, mixes production plan components and processes used to produce pre-cast concrete with skills for programming, organising and controlling the production of pre - cast concrete manufacturing processes. The competencies contained in this unit standard form part of the Elective learning of this qualification and extend beyond the mechanical completion of tasks associated with the production of pre-cast concrete and contribute towards the professional development of the learner by equipping him/her with enhanced knowledge and skills for the effective supervision of pre-cast concrete manufacturing processes that are carried out in accordance with Occupational Health and Safety Legislation and Regulations and industry requirements for cost-effective and quality workmanship completed within prescribed deadlines. This unit standard further contributes to socio-economic transformation in that learners will be able to undergo RPL-assessment and receive recognition for previous learning and experience, thereby enhancing the employability and career prospects of learners within the Civil Engineering Construction field. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following competencies will support the learner in the achievement of this unit standard:
|
UNIT STANDARD RANGE |
The typical scope of this unit standard:
Assessment against this unit standard must be undertaken on site. On site refers to a wide range of building and construction environments within which trade skills are required, and includes concrete production and concrete construction sites. Specific range statements are provided in the body of the unit standard where they apply to particular specific outcomes or assessment criteria. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Identify and describe the materials used in pre-cast concrete production. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Types of materials are identified as per workplace procedure |
ASSESSMENT CRITERION 2 |
Materials are described as to their application and suitability for pre-cast concrete manufacturing |
ASSESSMENT CRITERION 3 |
Storage and handling of materials is explained |
SPECIFIC OUTCOME 2 |
Demonstrate knowledge of pre-cast concrete mixes. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Pre-cast concrete elements are classified in accordance with manufacturing specifications |
ASSESSMENT CRITERION 2 |
The properties of pre-cast concrete materials are described in terms of their origin, manufacture, grade, and applicability to pre-cast mixes |
ASSESSMENT CRITERION 3 |
The properties of aggregates used in pre-cast mixes are described in terms of their source, supply and grading |
ASSESSMENT CRITERION 4 |
The sampling and testing of concrete materials are described in accordance with specifications |
SPECIFIC OUTCOME 3 |
Understand and explain the components and processes of pre-cast concrete production plants. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Pre-cast concrete plants are describe in terms of their layout and components |
ASSESSMENT CRITERION 2 |
Concrete batching plants are described in terms of their processes |
ASSESSMENT CRITERION 3 |
The operation of pre-cast concrete production plants are described in terms of their process controls |
ASSESSMENT CRITERION 4 |
The curing process of pre-cast elements are described in terms of accelerated strength |
ASSESSMENT CRITERION 5 |
The testing of pre-cast elements are described in accordance with specifications |
SPECIFIC OUTCOME 4 |
Programme, organise and control production. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Resource requirements are identified in accordance with specifications |
ASSESSMENT CRITERION 2 |
Work sequences and reporting procedures are planned, programmed and communicated in accordance with company procedures |
ASSESSMENT CRITERION 3 |
Record keeping is described and applied as per company procedure |
ASSESSMENT CRITERION 4 |
The scheduling of production is set out as per workplace procedures |
ASSESSMENT CRITERION 5 |
The manufacturing programme is evaluated |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems
Evident in the following specific outcomes and assessment criteria: Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD CCFO WORKING |
Work effectively with others
Evident in the following specific outcomes and assessment criteria: Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD CCFO ORGANISING |
Employ self management
Evident in the following specific outcomes and assessment criteria Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD CCFO COLLECTING |
Manage information
Evident in the following specific outcomes and assessment criteria Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively
Evident in the following specific outcomes and assessment criteria: Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD CCFO SCIENCE |
Demonstrate scientific and technological competence
Evident in the following specific outcomes and assessment criteria: Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD CCFO DEMONSTRATING |
Understand contextual world-systems
Evident in the following specific outcomes and assessment criteria: Identify and describe the materials used in pre-cast concrete production Demonstrate knowledge of pre-cast concrete mixes Understand and explain the components and processes of pre-cast concrete production plants Programme, organise and control production |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
N/A |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 65949 | Further Education and Training Certificate: Supervision of Construction Processes | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
Elective | 49053 | National Certificate: Supervision of Construction Processes | Level 4 | Level TBA: Pre-2009 was L4 | Passed the End Date - Status was "Reregistered" |
2018-06-30 | Was CETA until Last Date for Achievement |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | AVUXENI COMPUTER ACADEMY KZN |
2. | Big Tree Group |
3. | Certified Training Solutions (Pty) Ltd |
4. | Eastcape Training Centre |
5. | Eskilz College (Pty) Ltd |
6. | Pro Skills Development (Pty) Ltd |
7. | Raubex Construction Pty (Ltd) |
8. | SEDA Construction Incubator Trust |
9. | Sonani Training and Communications |
10. | South African Value Education (Pty) Ltd |
11. | Thabomeleng |
12. | Training Force (Pty) Ltd |
13. | Zama Training & Development cc |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |