All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install control valves |
SAQA US ID | UNIT STANDARD TITLE | |||
119077 | Install control valves | |||
ORIGINATOR | ||||
SGB Building Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Building Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 2 | NQF Level 02 | 3 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
Purpose of the unit standard:
The qualifying learner is capable of: This unit standard will be useful to people who work in the civil construction industry. People credited with this unit standard are able to demonstrate knowledge of pipelaying activities and are able to prepare and install control valves. Demonstrating knowledge of civil construction plant, equipment, and activities The contribution to the national skills development strategy is the key developmental interface between learners and new competencies to be achieved. Learners who master the applied competence described in this unit standard will contribute to the development of a professional community of civil engineering construction concreting practitioners who are able to competently use science and technology when conducting routine site tests to fresh and hardened concrete. The contribution to socio-economic transformation is that learners will be able to undergo rpl-assessment and thereby receive recognition for previous learning and experience. This in turn will enhance the employability and career prospects of learners employed in this sector. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
NQF 1 Numeracy and NQF 1 Literacy
The following knowledge, skills attitude and/or equivalent: It is assumed that people starting to learn towards this unit standard are already able to: |
UNIT STANDARD RANGE |
Air Valves, Gate valves, Sluice Valves, Stop Valves, Scour Valves, Hydrants
Testing should include visual alignment, and water and air pressure tests. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Control valve installation resources are identified and procured. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Prescribed resources are identified and Procured. |
ASSESSMENT CRITERION 2 |
All tools, equipment and personal protective equipment required for the task are identified and ensured to be functional, and are ready for use at work area. |
ASSESSMENT CRITERION 3 |
Resources are handled and stored in accordance with code of practice |
SPECIFIC OUTCOME 2 |
Prepare the work area before installation of control valves. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Work area is checked for hazards. All hazards are identified and corrective action is taken in line with worksite housekeeping procedures. |
ASSESSMENT CRITERION 2 |
All legislated safety precautions are adhered to in terms of work carried out below ground level. |
ASSESSMENT CRITERION 3 |
The work area is neat, free of obstructions, water, and loose material, within specification tolerances, and adheres to all design specifications in accordance with given instructions and drawings. |
ASSESSMENT CRITERION 4 |
The area is set out to line and level to receive the control valves in accordance with contract requirements. |
SPECIFIC OUTCOME 3 |
Install control valves pipes. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Work is carried out in accordance with work place safety requirements. |
ASSESSMENT CRITERION 2 |
Tools and equipment are used in accordance with their designed purpose. |
ASSESSMENT CRITERION 3 |
Personal protective equipment is used as required in accordance with the OHS Act. |
ASSESSMENT CRITERION 4 |
Control valves are laid neat and true to line and level within specification tolerances, and adhere to all design specifications in accordance with given instructions. |
ASSESSMENT CRITERION 5 |
The control valves are installed within industry acceptable time frames. |
SPECIFIC OUTCOME 4 |
Finish the installation of control valves. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The control valves is cleaned and disinfected according to contract requirements. |
ASSESSMENT CRITERION 2 |
The control valves are tested in accordance with the specifications. |
ASSESSMENT CRITERION 3 |
The installation of control valves is finished-off to contract requirements. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems
Specific outcome: Assessment criteria: |
UNIT STANDARD CCFO WORKING |
Work effectively with others
Specific outcome: Assessment criteria: |
UNIT STANDARD CCFO ORGANISING |
Employ self management
Specific outcome: Assessment criteria: |
UNIT STANDARD CCFO COLLECTING |
Manage information
Specific outcome: Assessment criteria: |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively
Specific outcome: Assessment criteria: |
UNIT STANDARD CCFO SCIENCE |
Demonstrate scientific and technological competence
Specific outcome: Assessment criteria: |
UNIT STANDARD CCFO DEMONSTRATING |
Understand contextual world-systems
Specific outcome: Assessment criteria: |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Supplementary information:
Acts, regulations, specifications and standards applicable to this unit standard: (i) Occupational health and safety act 1993. (ii) Gnr 1010 of 18 july 2003: construction regulations 2003. (iii) National environmental management act (no.107 of 1998) (iv) South african bureau of standards. (v) National building regulations. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 49411 | General Education and Training Certificate: Construction | Level 1 | NQF Level 01 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
Elective | 49410 | National Certificate: Construction | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
Elective | 96402 | National Certificate: Hot Water System Installation | Level 2 | NQF Level 02 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |