SAQA All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.
SOUTH AFRICAN QUALIFICATIONS AUTHORITY 
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: 

Plan organize and control the installation of drainage structures for stormwater flow 
SAQA US ID UNIT STANDARD TITLE
15195  Plan organize and control the installation of drainage structures for stormwater flow 
ORIGINATOR
SGB Civil Engineering Construction 
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY
-  
FIELD SUBFIELD
Field 12 - Physical Planning and Construction Civil Engineering Construction 
ABET BAND UNIT STANDARD TYPE PRE-2009 NQF LEVEL NQF LEVEL CREDITS
Undefined  Regular  Level 4  NQF Level 04  10 
REGISTRATION STATUS REGISTRATION START DATE REGISTRATION END DATE SAQA DECISION NUMBER
Passed the End Date -
Status was "Reregistered" 
2018-07-01  2023-06-30  SAQA 06120/18 
LAST DATE FOR ENROLMENT LAST DATE FOR ACHIEVEMENT
2026-06-30   2029-06-30  

In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise.  

This unit standard does not replace any other unit standard and is not replaced by any other unit standard. 

PURPOSE OF THE UNIT STANDARD 
Learners who are assessed as competent against this unit standard will be able to plan, organize and control the installation of drainage structure for storm-water flow.

This competence forms part of the Elective learning and represents a specific context of supervision, i.e. plan organize and control the installation of drainage structures for storm water flow in a civil engineering construction context

It contributes to the development of a professional community of Civil Engineering Construction Supervisors. The contribution to The National Skills Development Strategy is the key developmental interface between learners and new competencies to be achieved.

Its contribution to socio-economic transformation is that learners would be able to undergo RPL-assessment and thereby receive recognition for previous learning and experience. The employability and career prospects of learners can therefore be enhanced by this qualification. 

LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING 
ABET level 4 Literacy and Numeracy. 

UNIT STANDARD RANGE 
  • Installation of concrete pipes, Armco pipes, pre-cast concrete culverts, chutes, channels, subsoil drains.
  • The construction of manholes, catch-pits, in and outlets to culverts, concrete kerbs and channels, concrete v-drains, gabion baskets, reno mattresses. 

  • Specific Outcomes and Assessment Criteria: 

    SPECIFIC OUTCOME 1 
    Identify and procure resources. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Tools and minor plant types are identified to execute tasks. 

    ASSESSMENT CRITERION 2 
    2. Fuel supply and maintenance activities are planned. 

    ASSESSMENT CRITERION 3 
    3. Protective clothing and first aid kit identified and procured that will comply with the Occupational Health and Safety act requirements. 

    ASSESSMENT CRITERION 4 
    4. Road signs and traffic control devices identified and procured that will comply with working safely in a road environment. 

    SPECIFIC OUTCOME 2 
    Calculate material quantities, procure and store material. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Material quantities calculated from drawings and project specifications. 

    ASSESSMENT CRITERION 2 
    2. Material procured according to organizational procedures. 

    ASSESSMENT CRITERION 3 
    3. Material transported and stored as required for cost effective working. 

    SPECIFIC OUTCOME 3 
    Set out work. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Survey controls are established for setting out purposes. 

    ASSESSMENT CRITERION 2 
    2. Drainage system set out according to project specification. 

    SPECIFIC OUTCOME 4 
    Execute the installation of drainage systems. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Program for installation work is prepared. 

    ASSESSMENT CRITERION 2 
    2. The work is executed in compliance with project specifications or departmental manuals. 

    ASSESSMENT CRITERION 3 
    3. Records of labor, material and plant used captured on a daily basis. 

    ASSESSMENT CRITERION 4 
    4. Laboratory test identified and executed to ensure quality of work complies to project specification. 

    ASSESSMENT CRITERION 5 
    5. Lines and levels checked to ensure work complies to project specification. 

    ASSESSMENT CRITERION 6 
    6. Deficiencies identified in terms of meeting program. 

    ASSESSMENT CRITERION 7 
    7. Remedial action recommended to supervisor. 

    ASSESSMENT CRITERION 8 
    8. Precautions to safeguard environment is identified and implemented. 

    SPECIFIC OUTCOME 5 
    Control productivity of installation work. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    1. Production targets for the various tasks are determined and compared with industry norms. 

    ASSESSMENT CRITERION 2 
    2. Production targets are set for the various tasks. 

    ASSESSMENT CRITERION 3 
    3. Compliance to production targets is monitored. 

    ASSESSMENT CRITERION 4 
    4. Remedial action is identified where targets are not met. 


    UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS 
  • Anyone assessing a learner or moderating the assessment of a learner against this unit standard must be registered as an assessor with the CETA - ETQA for "The National Certificate in the Supervision of Construction Processes".
  • Any institution offering learning that will enable the achievement of this unit standard must be accredited as a provider with the CETA - ETQA.
  • CETA - ETQA, or other ETQA's who have a Memorandum of Understanding in place with CETA-ETQA, would be responsible for moderation of learner achievements of learners who meet the requirements of this qualification. 

  • UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE 
  • Installation techniques for concrete pipes, pre-cast culverts, Armco pipes, chutes, channels.
  • Construction techniques for manholes, catch-pits, in and out lets for drainage structures, kerbs and channels, concrete v-drains, sub-soil drainage.
  • Protective clothing and equipment used in the installation of drainage structures.
  • Occupational heath and safety regulations to working in confined spaces.
  • Procedures to control traffic during construction activities. 

  • UNIT STANDARD DEVELOPMENTAL OUTCOME 
    N/A 

    UNIT STANDARD LINKAGES 
    N/A 


    Critical Cross-field Outcomes (CCFO): 

    UNIT STANDARD CCFO IDENTIFYING 
    Identify and solve problems.

    Specific Outcome:
    Execute the installation of drainage systems.

    Assessment Criteria:
    Program for installation work is prepared. 

    UNIT STANDARD CCFO WORKING 
    Work effectively with others.

    Specific Outcome:
    Execute the installation of drainage systems.

    Assessment Criteria:
    Remedial action recommended to supervisor. 

    UNIT STANDARD CCFO ORGANISING 
    Employ self management.

    Specific Outcome:
    Control productivity of installation.

    Assessment Criteria:
    Production targets for the various tasks are determined and compared with industry norms. 

    UNIT STANDARD CCFO COLLECTING 
    Manage information.

    Specific Outcome:
    Execute the installation of drainage systems.

    Assessment Criteria:
    Program for installation work is prepared. 

    UNIT STANDARD CCFO COMMUNICATING 
    Communicate effectively.

    Specific Outcome:
    Execute the installation of drainage systems.

    Assessment Criteria:
    Remedial action recommended to supervisor. 

    UNIT STANDARD CCFO SCIENCE 
    Demonstrate scientific and technological competence.

    Specific Outcome:
    Execute the installation of drainage systems.

    Assessment Criteria:
    Lines and levels checked to ensure work complies to project specification. 

    UNIT STANDARD CCFO DEMONSTRATING 
    Understand Contextual world-systems.

    Specific Outcome:
    Execute the installation of drainage systems.

    Assessment Criteria:
    Precautions to safeguard environment is identified and implemented. 

    UNIT STANDARD ASSESSOR CRITERIA 
    N/A 

    REREGISTRATION HISTORY 
    As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. 

    UNIT STANDARD NOTES 
    N/A 

    QUALIFICATIONS UTILISING THIS UNIT STANDARD: 
      ID QUALIFICATION TITLE PRE-2009 NQF LEVEL NQF LEVEL STATUS END DATE PRIMARY OR DELEGATED QA FUNCTIONARY
    Elective  65949   Further Education and Training Certificate: Supervision of Construction Processes  Level 4  NQF Level 04  Passed the End Date -
    Status was "Reregistered" 
    2023-06-30  CETA 
    Elective  23682   National Certificate: Supervision of Civil Engineering Construction Processes: Labour Intensive Construction  Level 4  NQF Level 04  Passed the End Date -
    Status was "Registered" 
    2004-06-09  Was CETA until Last Date for Achievement 
    Elective  23673   National Certificate: Supervision of Civil Engineering Construction Processes: Water and Waste Water  Level 4  NQF Level 04  Passed the End Date -
    Status was "Registered" 
    2004-06-09  Was CETA until Last Date for Achievement 
    Elective  49053   National Certificate: Supervision of Construction Processes  Level 4  Level TBA: Pre-2009 was L4  Passed the End Date -
    Status was "Reregistered" 
    2018-06-30  Was CETA until Last Date for Achievement 


    PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: 
    This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here.
     
    1. AVUXENI COMPUTER ACADEMY KZN 
    2. Big Tree Group 
    3. Certified Training Solutions (Pty) Ltd 
    4. Construction Resource Development College 
    5. Eastcape Training Centre 
    6. Eskilz College (Pty) Ltd 
    7. Pro Skills Development (Pty) Ltd 
    8. Raubex Construction Pty (Ltd) 
    9. SEDA Construction Incubator Trust 
    10. Sonani Training and Communications 
    11. South African Value Education (Pty) Ltd 
    12. Thabomeleng 
    13. Training Force (Pty) Ltd 
    14. Zama Training & Development cc 



    All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.