All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Wire and commission domestic or commercial electrical circuits |
SAQA US ID | UNIT STANDARD TITLE | |||
258968 | Wire and commission domestic or commercial electrical circuits | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 8 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
10265 | Wire and commission domestic electrical circuits | Level 3 | NQF Level 03 | 8 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering; Generation; Distribution; Transmission, Construction and Renewable Energy Sector.
A person credited with this unit standard will able to: This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical engineering and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and/or equivalent:
|
UNIT STANDARD RANGE |
Electrical installation includes residential, commercial, single and three phase supplies. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan to wire and commission domestic or commercial circuits. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job instruction is interpreted and a sequence of operation is determined. |
ASSESSMENT CRITERION 2 |
Applicable electrical drawings are correctly interpreted and selected to meet job requirements. |
ASSESSMENT CRITERION 3 |
Equipment and personal protective equipment is selected, inspected and checked for functionality and safety prior to commencement. |
ASSESSMENT CRITERION 4 |
Safety procedures related to job requirements and work site procedures are obtained. |
ASSESSMENT CRITERION 5 |
Different types/sizes of wire conductors are identified and selected according to job instructions. |
ASSESSMENT CRITERION 6 |
Appropriate tools are identified and selected to meet the requirements of the task according to statutory requirements. |
SPECIFIC OUTCOME 2 |
Prepare to wire and commission domestic or commercial circuits. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Wire ways are identified and checked to be ready for the installation of wires/conductors or cables. |
ASSESSMENT CRITERION 2 |
Work site is inspected for safety and hazards and corrective action is taken according to statutory requirements. |
ASSESSMENT CRITERION 3 |
Wire way installation is checked for the placing/mounting of inspection/end/termination boxes, end products and various obstacles so as to take necessary corrective action or processes when wiring domestic or commercial circuits. |
ASSESSMENT CRITERION RANGE |
SPECIFIC OUTCOME 3 |
Wire domestic or commercial circuits. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate tools are selected and used correctly as per manufacturer's specifications and work site standards. |
ASSESSMENT CRITERION 2 |
Draw wire is inserted into wire way in preparation for pulling through of wires into wire ways or through/around obstacles. |
ASSESSMENT CRITERION 3 |
Circuits are wired separately into wire ways depending on the circuit requirements to comply with SANS standards. |
ASSESSMENT CRITERION RANGE |
ASSESSMENT CRITERION 4 |
Maximum amounts of wires per size of wire ways and type of circuit is adhered to as per SANS standards. |
ASSESSMENT CRITERION 5 |
Correct colour coded wires are used in wire ways as per the SANS and job requirements. |
ASSESSMENT CRITERION 6 |
Wiring must be done in accordance with SANS standards. |
ASSESSMENT CRITERION RANGE |
Various sizes of wiring and flexible cabling for different circuits, terminated with compression glands, bends radius and inspection boxes. |
ASSESSMENT CRITERION 7 |
All connections must be correct, tight and required slack as per job requirements in accordance with SANS. |
SPECIFIC OUTCOME 4 |
Commission domestic or commercial circuits. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Distribution board is inspected, checked, tested to ensure that protection devices are operational; wiring and connections are correct. |
ASSESSMENT CRITERION 2 |
All inspection boxes and terminations are inspected and checked to be correct before circuit is energised/commissioned. |
ASSESSMENT CRITERION 3 |
Tests are conducted on circuits for requirements and energising to ensure compliance with work site procedures, SANS standards and safety regulations. |
ASSESSMENT CRITERION RANGE |
Continuity tests, insulation tests and polarity test. |
ASSESSMENT CRITERION 4 |
Different circuits are energised/commissioned individually to ensure that it is correct. |
ASSESSMENT CRITERION RANGE |
Lighting circuits, plug circuits, geyser circuit, stove circuit. |
ASSESSMENT CRITERION 5 |
Tests are conducted on specific circuits to ensure that earth leakage protection is operational within the stipulated rating. |
SPECIFIC OUTCOME 5 |
Complete the wiring and commissioning of domestic or commercial circuits. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Electrical installations are labelled as per SANS 10142-1. |
ASSESSMENT CRITERION 2 |
All connections are tight and mechanically sound to ensure electrical safety. |
ASSESSMENT CRITERION 3 |
Test readings are recorded using appropriate documentation and forms as specified in work site procedures. |
ASSESSMENT CRITERION 4 |
The work area is cleaned and waste disposed of in the appropriate manner. |
ASSESSMENT CRITERION 5 |
Work area is restored to serviceable condition according to statutory requirements. |
ASSESSMENT CRITERION 6 |
Appropriate tools are cared for and stored according to work site requirements. |
ASSESSMENT CRITERION 7 |
Reports/documentation and drawing are updated and returned to source according to statutory requirements. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems related to the achievement of relevant competencies. |
UNIT STANDARD CCFO ORGANISING |
Organise oneself and ones activities so that all requirements are met in achieving competence in the wiring of premises. |
UNIT STANDARD CCFO COLLECTING |
Collect, evaluate, organise and critically evaluate information related to wiring of premises so that these are accurately interpreted into application performance standards. |
UNIT STANDARD CCFO COMMUNICATING |
Understand the world as a set of related systems in that are interrelated with the overall safe and lawful. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard 10265, "Wire and commission domestic electrical circuits", Level 3, 8 credits. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 72051 | National Certificate: Electrical Engineering | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | Better Best Agri Development |
2. | CLEAN HEAT ENERGY SAVING SOLUTIONS (PTY) LTD |
3. | DR HE MAEPA INSTITUTE |
4. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
5. | KP ACADEMY (PTY) LTD |
6. | Majuba TVET College |
7. | MSC ARTISAN ACADEMY |
8. | POWER SYSTEMS TRAINING, CAPE TOWN |
9. | Protech Training (Pty) Ltd |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |