All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Install and commission direct-on-line AC rotating machines and control gear |
SAQA US ID | UNIT STANDARD TITLE | |||
259077 | Install and commission direct-on-line AC rotating machines and control gear | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 10 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
10261 | Install and Commission Single Phase AC Machines and Control Gear | Level 3 | NQF Level 03 | 8 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the Electrical Engineering, Generation, Distribution, Transmission, Construction, Mining and Renewable Energy Sectors. This unit standard is intended to promote general skills, knowledge and understanding required for the installation, connecting and testing of direct-on-line AC rotating machines and control gear in order to ensure knowledgeable and informed workers.
A person credited with this unit standard will be capable of: This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within all sectors of the electrical engineering field. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and/or equivalent:
|
UNIT STANDARD RANGE |
The range of this unit standard applies to the following direct-on-line AC rotating machines and control gear:
Single phase AC motors which may include, but are not limited to: Single phase AC control gear may include, but are not limited to: Installation and commissioning of single phase direct-on-line AC rotating machines and control gear may include, but are not limited to: Three phase AC motors which may include, but are not limited to: Three phase AC control gear may include, but are not limited to: Installation and commissioning of three phase direct-on-line AC rotating machines and control gear may include, but are not limited to: |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan and prepare for the work task. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job instructions are obtained and the sequence of the task is planned in accordance with accepted company and work site procedures. |
ASSESSMENT CRITERION 2 |
Appropriate test and measuring equipment, hand tools and material are selected and examined according to task and worksite requirements. |
ASSESSMENT CRITERION 3 |
Direct-on-line AC rotating machines and control gear are correctly selected and tested according to statutory requirements. |
ASSESSMENT CRITERION 4 |
Safety procedures are obtained and interpreted to meet task requirements. |
ASSESSMENT CRITERION 5 |
The required personal protective equipment is selected, examined and used in a manner that protects the individual in accordance with specified requirements. |
SPECIFIC OUTCOME 2 |
Install direct-on-line AC rotating machines and control gear. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The worksite is examined for hazardous and sub-standard conditions and corrective action taken where necessary according to safe work procedures and critical task analyses. |
ASSESSMENT CRITERION 2 |
Hazards and associated risks directly related to the installation of direct-on-line AC rotating machines and control gear is identified and addressed in accordance with specified requirements. |
ASSESSMENT CRITERION 3 |
Single-phase A.C. rotating machines and control gear are installed according to worksite procedures and statutory requirements. |
ASSESSMENT CRITERION 4 |
Three-phase A.C. rotating machines and control gear are installed according to worksite procedures and statutory requirements. |
ASSESSMENT CRITERION 5 |
Appropriate tools are used to meet the job requirements. |
ASSESSMENT CRITERION 6 |
Reasons for the specific selection and use of the appropriate tools are explained with reference to the type and application. |
SPECIFIC OUTCOME 3 |
Connect direct-on-line AC rotating machines and control gear. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate tools are used without injury to self and others according to job requirements. |
ASSESSMENT CRITERION 2 |
Personal protective equipment is used in a manner that protects the individual in accordance with specified requirements. |
ASSESSMENT CRITERION 3 |
Single phase AC rotating machines and control gear are connected according to electrical diagrams, worksite procedures and statutory requirements. |
ASSESSMENT CRITERION 4 |
Three phase AC rotating machines and control gear are connected according to electrical diagrams, worksite procedures and statutory requirements. |
ASSESSMENT CRITERION 5 |
Connections are mechanical sound and electrically continuous according to accepted engineering practices. |
ASSESSMENT CRITERION 6 |
Hazards and risks directly related to the connecting of direct-on-line AC rotating machines and control gear is identified and addressed in accordance with worksite procedure. |
ASSESSMENT CRITERION 7 |
Safety and correct environmental practices are followed before, during and after the maintenance and repair activities according to statutory and worksite requirements. |
SPECIFIC OUTCOME 4 |
Commission direct-on-line AC rotating machines and control gear. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Appropriate test and measuring equipment and hand tools are used to meet the job requirements. |
ASSESSMENT CRITERION 2 |
Measuring and testing equipment, and hand tools selected is used correctly and safely in accordance with manufacture's instructions. |
ASSESSMENT CRITERION 3 |
Tests are carried out according to worksite procedures and statutory requirements. |
ASSESSMENT CRITERION RANGE |
Tests include but is not limited to:
|
ASSESSMENT CRITERION 4 |
Tests are recorded and reported according to work site procedures. |
ASSESSMENT CRITERION 5 |
Final testing and commissioning is carried out and documentation completed in accordance with specified requirements. |
ASSESSMENT CRITERION RANGE |
Final testing and commissioning include but is not limited to:
|
ASSESSMENT CRITERION 6 |
Where applicable, non-conformances are identified and rectified in accordance with accepted best practice. |
ASSESSMENT CRITERION 7 |
Tools, material and equipment used are dealt with in accordance with specified requirements. |
ASSESSMENT CRITERION RANGE |
Dealing with tools, material and equipment include but is not limited to:
|
ASSESSMENT CRITERION 8 |
The workplace is cleaned to comply with specified housekeeping practices. |
ASSESSMENT CRITERION 9 |
The report on work performed is complete and complies with specified requirements. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
This embedded knowledge is the same as that for the maintenance US and should be reconsidered with regard to knowledge assumed to be in place.
Knowledge that will help me to understand and that I will be able to explain: |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
The ability of the candidate to identify sub-standard and hazardous conditions, to identify defects when testing and rectifying faults. |
UNIT STANDARD CCFO WORKING |
The ability and willingness of the candidate to accept and interpret work instructions correctly and in reporting work activities to superior. |
UNIT STANDARD CCFO ORGANISING |
The ability of the candidate to indicate what methods, tools and personal protective equipment is required and planning the work and determining a sequence of operation. |
UNIT STANDARD CCFO COLLECTING |
The ability of the candidate to reconcile the information obtained during testing of the direct-on-line AC rotating machines and control gear, and critically evaluating information related to the test results. |
UNIT STANDARD CCFO COMMUNICATING |
The appropriate communication with the relevant personnel with regard to the reporting of hazards and sub-standard conditions reporting to superior on work activities will indicate his/her proficiency in effective communication. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard , "Install and Commission Single Phase AC Machines and Control Gear", Level 3, 8 credits.
Supplementary Information: Specified Requirements: Specified and worksite requirements include legal and site-specific requirements and are contained in one or more of the following documents: Legal: Site-Specific: |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 72051 | National Certificate: Electrical Engineering | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | Better Best Agri Development |
2. | CLEAN HEAT ENERGY SAVING SOLUTIONS (PTY) LTD |
3. | DR HE MAEPA INSTITUTE |
4. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
5. | KP ACADEMY (PTY) LTD |
6. | Majuba TVET College |
7. | MSC ARTISAN ACADEMY |
8. | POWER SYSTEMS TRAINING, CAPE TOWN |
9. | Protech Training (Pty) Ltd |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |